n <br />ACC <br />CHANGE IN CONTRACT TIMES <br />Description Time <br />Original Contract Time: (days or dates) <br />Substantial Completion: 270 days - 5/23/2008 <br />Final Completion: 300 days - 6/22/2008 <br />Net change from previous Change Orders <br />No. 000 to 008A: (days) <br />Substantial Completion: 67 <br />Final Completion: 67 <br />Contract Time prior to this Change Order: (days or dates) <br />Substantial Completion: 357 days — 8/18/2008 <br />Final Completion: 387 days — 9/17/2008 <br />Net increase this Change Order, (days or dates) <br />Substantial Completion: -49- days <br />Final Completion: -49- davs <br />Contract Time with all approved Change (days or dates) <br />Orders: <br />Substantial Completion: 393 days — 9/24/2008 <br />Final Completion: 423 days —10/23/2008 <br />By: <br />05NTRACTOR (Signature <br />410pE Cr. DIeo M-I,ti <br />ZZILC w v eOrfVe r77 <br />( ame and Title) <br />Date: (O - g —o e - <br />By: /` <br />ENGTNEignature) <br />Keith McCully, P.E., Indian <br />River County Stormwater <br />Engineer <br />Date: /4 - e -2o O <br />vV€D: <br />OIL" rm"nii?VA <br />Go. "Sandrg L. Bbwden <br />(Sig ature <br />Indian Rives County Board of <br />County Coi mmissioner.s <br />Date: October 14, 2008 <br />Change Order - Page 4 of 4 Change Order No. 009 <br />F:`Public WorksXeithMStormwater Projects' Main Relief Canal\Change Orders`,Change Order No. 009'Change Order No 009 - <br />FINAL.docx Last revised 9/27/01 <br />CHANGE IN CONTRACT PRICE: <br />Description <br />Amount <br />ontract Price <br />$3,3689799.60 <br />se from previous Change Orders <br />008A: <br />$240,055.55 <br />Contract Price prior to this Change Order: <br />$3,6089855.15 <br />Net Increase of this Change Order: <br />$1209780.34 <br />Contract Price with all approved Change <br />$397299635.49 <br />Orders: <br />CHANGE IN CONTRACT TIMES <br />Description Time <br />Original Contract Time: (days or dates) <br />Substantial Completion: 270 days - 5/23/2008 <br />Final Completion: 300 days - 6/22/2008 <br />Net change from previous Change Orders <br />No. 000 to 008A: (days) <br />Substantial Completion: 67 <br />Final Completion: 67 <br />Contract Time prior to this Change Order: (days or dates) <br />Substantial Completion: 357 days — 8/18/2008 <br />Final Completion: 387 days — 9/17/2008 <br />Net increase this Change Order, (days or dates) <br />Substantial Completion: -49- days <br />Final Completion: -49- davs <br />Contract Time with all approved Change (days or dates) <br />Orders: <br />Substantial Completion: 393 days — 9/24/2008 <br />Final Completion: 423 days —10/23/2008 <br />By: <br />05NTRACTOR (Signature <br />410pE Cr. DIeo M-I,ti <br />ZZILC w v eOrfVe r77 <br />( ame and Title) <br />Date: (O - g —o e - <br />By: /` <br />ENGTNEignature) <br />Keith McCully, P.E., Indian <br />River County Stormwater <br />Engineer <br />Date: /4 - e -2o O <br />vV€D: <br />OIL" rm"nii?VA <br />Go. "Sandrg L. Bbwden <br />(Sig ature <br />Indian Rives County Board of <br />County Coi mmissioner.s <br />Date: October 14, 2008 <br />Change Order - Page 4 of 4 Change Order No. 009 <br />F:`Public WorksXeithMStormwater Projects' Main Relief Canal\Change Orders`,Change Order No. 009'Change Order No 009 - <br />FINAL.docx Last revised 9/27/01 <br />