Laserfiche WebLink
ATTACHMENT 3 to WORK ORDER NO. 3 -EM <br />ADDITIONAL ENGINEERING SERVICES FOR EGRET MARSH REGIONAL <br />STORMWA TER PARK FINAL REDESIGN AND CONSTRUCTION <br />TIME FOR COMPLETION <br />The CONSULTANT's time -of -completion for engineering design services covered <br />by this Work Order depends on County staff's ability to get information to the <br />CONSULTANT. The engineering design portion of the work is anticipated to be complete <br />within 30 calendar days from the date the necessary information is transmitted to the <br />CONSULTANT by County staff. The CONSULTANT's time -of -completion for the <br />remainder of the work herein depends on the construction schedule determined by the <br />construction contract. Said construction schedule is anticipated to range from 300 to 360 <br />calendar days. <br />**END OF ATTACHMENT 3** <br />4 <br />C:Tocuments and SettingsNmanno\Local Settings\Temporary Internet FileslContent.OutookOGUO33FE\Malcolm Pimie Work Order <br />#3 -EM - FINAL.doc <br />