Indian River County Turner
<br /> Administration Complex
<br /> Final GMP Summary
<br /> Qualifications & Assumptions
<br /> Report Date: August 16, 2005
<br /> Drawings :
<br /> 1 Any special loading for joists marked SP are excluded from the GMP . No loads were
<br /> given .
<br /> 2 Molded cover top as shown for the atrium balcony railings is not included . The atrium rail
<br /> has a radiused top , square posts and infill panel .
<br /> 3 The handrails at the exit stairs are included in the GMP as 6 " line standard painted steel .
<br /> Bid Package 6 Millwork
<br /> Specifications :
<br /> no clarifications
<br /> Drawings :
<br /> 1 All the following millwork , which is shown in elevation on the drawings , is included in the
<br /> GMP : Rooms 1 . 1 - 101 a , 1 . 1 - 108 , 1 . 1 - 109 , 1 . 1 - 2155 1 . 1 -2173 1 . 1 - 2189 1 . 1 -4015
<br /> 1 . 1 - 404 , 1 , 1 -
<br /> 4065 1 . 1 -4207 1 . 1 - 4283 1 , 1 -50211 , 1 -5059 1 , 2 -21211 . 2 - 228 , 1 . 2 -40311 , 2- 5143 1 . 2 -603 ,
<br /> 2 . 1 -
<br /> 226 , and 2 . 2-324 .
<br /> 2 All the following millwork items are included as an allowance in the GMP ; Rooms 1 . 1 - 101 ,
<br /> 1 . 1 - 102 , 1 . 1 - 116 , 1 . 1 -205 , 1 . 1 - 303 , 1 . 1 -408 , 1 . 1 - 411 , 1 . 1 -501 , 1 . 2- 511
<br /> , 1 . 2 - 512 , 1 . 2- 613 ,
<br /> 1 . 2-704 , 1 . 2 - 7053 1 . 2-8015 1 . 2- 803 , 2 . 1 -2029 2 . 1 -3035 2 . 1 -4021 2 . 1 - 604 , 2 . 1 - 622 , and
<br /> 2 . 2-
<br /> 302 .
<br /> 3 All the following millwork items are excluded from the GMP ; Rooms 1 . 1 -201 , 1 . 1 -2029 1 . 1 -
<br /> 203 , 1 . 1 -302 , 1 , 1 -40511 , 1 - 407 , 1 . 1 -4083 1 . 2- 106 , 2 . 1 -2015 2 . 1 -2185 2 . 1 -4015 2 . 1
<br /> -409 , 2 . 1 -
<br /> 5019 2 . 1 - 5035 2 . 1 - 601 , 2 . 1 -6039 2 . 1 -624 , 2 . 1 - 627 , and 2 . 2-315 .
<br /> 4 All wood base WB- 1 , crown molding , wood paneling , wood trim , and restroom countertops
<br /> are included in the GMP .
<br /> Bid Package 6a Cast Stone Columns
<br /> Specifications :
<br /> 1 Manufacturer' s standard finishes and colors are included in the GMP .
<br /> 2 Manufacturer' s standard warranty is included in the GMP .
<br /> 3 If a mock up is required , it shall serve as part of the final installation if approved .
<br /> Drawings :
<br /> 1 Manufacturer' s existing mold , which may differ slightly in dimensions but fully incorporates
<br /> design intent , may be used as contractor' s option .
<br /> Page 9 d °