Co CONTRACTOR has carefully studied all: ( 1 ) reports of explorations and tests of
<br /> subsurface conditions at or contiguous to the Site and all drawings of physical
<br /> conditions in or relating to existing surface or subsurface structures at or contiguous to
<br /> the Site (except Underground Facilities) which have been identified in the
<br /> Supplementary Conditions as provided in paragraph 4 . 02 of the General Conditions
<br /> and (2) reports and drawings of a Hazardous Environmental Condition , if any , at the
<br /> Site which have been identified in the Supplementary Conditions as provided in
<br /> paragraph 4. 06 of the General Conditions.
<br /> E . CONTRACTOR has obtained and carefully studied (or assumes responsibility for
<br /> having done so) all examinations, investigations, explorations, tests, studies, and data
<br /> concerning conditions (surface , subsurface, and Underground Facilities) at or
<br /> contiguous to the Site which may affect cost, progress, or performance of the Work or
<br /> which relate to any aspect of the means, methods , techniques, sequences, and
<br /> procedures of construction to be employed by CONTRACTOR , including applying the
<br /> speck means, methods, techniques, sequences, and procedures of construction , if
<br /> any , expressly required by the Contract Documents to be employed by CONTRACTOR,
<br /> and safety precautions and programs incident thereto
<br /> F . CONTRACTOR does not consider that any further examinations, investigations,
<br /> explorations, tests, studies, or data are necessary for the performance of the Work at
<br /> the Contract Price, within the Contract Times, and in accordance with the other terms
<br /> and conditions of the Contract Documents,
<br /> G . CONTRACTOR is aware of the general nature of work to be performed by OWNER
<br /> and others at the Site that relates to the Work as indicated in the Contract Documents.
<br /> H . CONTRACTOR has correlated the information known to CONTRACTOR, information
<br /> and observations obtained from visits to the Site , reports and drawings Identified in the
<br /> Contract Documents, and all additional examinations, investigations, explorations ,
<br /> tests, studies, and data with the Contract Documents,
<br /> I . CONTRACTOR has given ENGINEER written notice of all conflicts, errors, ambiguities,
<br /> or discrepancies that CONTRACTOR has discovered in the Contract Documents , and
<br /> the written resolution thereof by ENGINEER is acceptable to CONTRACTOR.
<br /> J . The Contract Documents are generally sufficient to indicate and convey understanding
<br /> of all terms and conditions for performance and furnishing of the Work.
<br /> ARTICLE 9 - CONTRACT DOCUMENTS
<br /> 9. 01 Contents
<br /> A. The Contract Documents consist of the following :
<br /> 1 . This Agreement (pages 00520- 1 to 00520-8 , inclusive) ;
<br /> 2 . Section 00610 - Performance Bond (pages 00610-1 to 00610-5 , inclusive) ;
<br /> 3 . Section 00612 - Payment Bond (pages 00612- 1 to 00612-5, inclusive) ;
<br /> 12 Agreement 1117
<br /> 00520 - 5
<br /> Mocumwft aid S9M p WbNimM3eW PMkJ02V Con"dt PedwgM12 Apreament 1117.doe Rev. 05101
<br />
|