Laserfiche WebLink
Approval -Major and Minor Construction Changes, Form No. 700-01047. <br />23. TIME EXTENSIONS. <br />The County may grant an extension of Contract Time when it add s new work items or provides for <br />unforeseen work, provided that the additional work actually impacts the contract critical path completion <br />schedule. The City may also grant an extension of Contract Time when a critical path item of work is delayed <br />by factors not reasonably anticipated or foreseeable at the time of bid or if failure of the County to fulfill an <br />obligation under the contract results in delays to the schedule critical path. The County may consider the <br />delays in delivery of materials or equipment that affect progress on a critical item of work as the basis for <br />granting a time extension if such delays are beyond the control of the Contractor. Requests for time <br />extensions due to delay in the delivery of custom manufactured equipment or fixtures will not be considered <br />unless the contractor furnishes documentation that the order was placed in a timely manner and the lack of <br />such equipment cased a delay in progress on a critical item. <br />Extensions of Contract Time will not be granted for delays due to the fault or negligence of the <br />Contractor. <br />No allowance for inclement weather should be made in establishing the Contract Time, The County <br />may grant time extensions on a day for day basis for delays caused only by inclement weather conditions that <br />prevent the contractor from productively performing critical path items where: (i) the contractor is unable to <br />work at least 50% of the day on a pre -determined critical path item due to the weather; or (ii) the contractor <br />must make major repairs to work damaged by weather provided that the damage is not due to the contractor's <br />failure to perform and that the contractor is unable to work at least 50% of the day on pre -determined critical <br />path items. <br />24. LIQUIDATED DAMAGES <br />Applicable liquidated damages will be assessed in the following amount: $713.00 per day <br />25. CONTRACT CLAIMS BY CONTRACTOR <br />Should the contractor intend to file a claim for additional monetary compensation, time or other <br />adjustments to the contract and the County disputes the contractor's entitlement to the claim or the impact of <br />the claim, Contractor must provide written notification to the County of contractor's intent to file a claim. This <br />notice must be given before the contractor begins any work on which the claim is based. Failure of the <br />contractor to notify the County before beginning work on any disputed items waives the contractor's right to <br />claim. The contractor's notice of intent to file a claim should contain: <br />(1) A statement as to what changed, including a description of the nature and extent of the <br />change. <br />(2) An indication of who directed or what caused the change. <br />(3) A description of how the change has or will impact the contractor, including reference to any <br />impacted critical activities on the contractor's latest accepted schedule update. <br />(4) A statement of damages, or an estimate of damages if available, detailing the amount of <br />compensation, time and/or other adjustment to the contract that is being requested. <br />26. DRUG-FREE WORKPLACE CERTIFICATION <br />In accordance with Florida Statute 287.087, the bidder shall certify that it has and will maintain a drug-free <br />workplace. The bidder shall complete and submit with its bid proposal the attached certification. Failure to <br />include an executed certification may cause the bid proposal to be considered non-responsive. <br />23 <br />F:\Engineering\Capital Projects\0604-12th St Sidewalk Improve between 43rd Ave & 27th Ave\0604 Federal <br />Contract Provisions.doc =9=8 3M.34 PM <br />