thereby, however, CONTRACTOR shall not be liable 2 . 07 Initial Acceptance of Schedules <br /> to OWNER or ENGINEER for failure to report any <br /> conflict, error, ambiguity, or discrepancy in the A. Unless otherwise provided in the Contract <br /> Contract Documents unless CONTRACTOR knew or Documents , at least ten days before submission of the <br /> reasonably should have known thereof. first Application for Payment a conference attended by <br /> CONTRACTOR, ENGINEER, and others as appropri- <br /> B . Preliminary Schedules. Within ten days after ate will be held to review for acceptability to ENGI- <br /> the Effective Date of the Agreement ( unless otherwise NEER as provided below the schedules submitted in <br /> specified in the General Requirements) , CONTRAC- accordance with paragraph 2 .05 . 13 . CONTRACTOR <br /> TOR shall submit to ENGINEER for its timely review: shall have an additional ten days to make corrections <br /> and adjustments and to complete and resubmit the <br /> 1 . a preliminary progress schedule schedules . No progress payment shall be made to <br /> indicating the times (numbers of days or dates) CONTRACTOR until acceptable schedules are <br /> for starting and completing the various stages submitted to ENGINEER, <br /> of the Work, including any Milestones specified <br /> in the Contract Documents; 1 . The progress schedule will be <br /> acceptable to ENGINEER if it provides an <br /> 2 , a preliminary schedule of Shop orderly progression of the Work to completion <br /> Drawing and Sample submittals which will list within any specified Milestones and the <br /> each required submittal and the times for sub- Contract Times . Such acceptance will not <br /> mitting , reviewing , and processing such impose on ENGINEER responsibility for the <br /> submittal ; and progress schedule, for sequencing, scheduling , <br /> or progress of the Work nor interfere with or <br /> 3 . a preliminary schedule of values for relieve CONTRACTOR from CONTRACTOR's <br /> all of the Work which includes quantities and full responsibility therefor. <br /> prices of items which when added together <br /> equal the Contract Price and subdivides the 2 . CONTRACTOR's schedule of Shop <br /> Work into component parts in sufficient detail to Drawing and Sample submittals will be <br /> serve as the basis for progress payments acceptable to ENGINEER if it provides a <br /> during performance of the Work. Such prices workable arrangement for reviewing and <br /> will include an appropriate amount of overhead processing the required submittals , <br /> and profit applicable to each item of Work. <br /> 3 . CONTRACTOR's schedule of values <br /> C will be acceptable to ENGINEER as to form <br /> and substance if it provides a reasonable <br /> allocation of the Contract Price to component <br /> parts of the Work. <br /> ARTICLE 3 - CONTRACT DOCUMENTS : INTENT, <br /> AMENDING , REUSE <br /> 3 . 01 Intent <br /> Artonle-5 . <br /> A. The Contract Documents are comple- <br /> 2 . 06 Preconstruction Conference mentary; what is called for by one is as binding as if <br /> A, Within 49 days a#9F the GeRtFaGt Times staFt called for by all . <br /> B . It is the intent of the Contract Documents to <br /> describe a functionally complete Project (or part there- <br /> of) to be constructed in accordance with the Contract <br /> Documents . Any labor, documentation , services , <br /> materials , or equipment that may reasonably be <br /> inferred from the Contract Documents or from <br /> prevailing custom or trade usage as being required to <br /> produce the intended result will be provided whether <br /> or not specifically called for at no additional cost to <br /> OWNER. <br /> 00700 - General Conditions <br /> 00700 - 9 <br /> FAEngineering\Petition Paving\0522 list Rd. from 32nd Ave. to 35th Ave\Bid Documents\00700 - General Condilions.doc <br />