Laserfiche WebLink
B . Bonds and Insurances : The measurement for procuring and providing the : <br /> performance bond ; payment bond ; and the required insurances shall not exceed 2 - <br /> 1 /2 percent of the total Contract Amount unless justified by the Contractor. Adequate <br /> justification by the Contractor shall be copies of invoices or contracts between the <br /> Contractor and Surety or insurance broker for the specified bonds or insurances . <br /> C . Conformance with Project Conditions : The Measurement and Cost of complying with <br /> all the Contract Conditions , including those associated with project permits , which <br /> are not specified pay items shall be included in the lump sum pay items bid for the <br /> Project . This paragraph does not apply to unforeseen underground conditions or <br /> changes in the work which are included under the Change Order provisions of the <br /> Contract Conditions . <br /> D . Specified Pay Items : The method Of Measurement and the Cost for providing and <br /> installing the project as designed shall be as included in the Schedule of Contract <br /> Prices as listed in the Agreement and as may be further described in the Technical <br /> Specification Sections . <br /> 1 . 04 PAYMENT <br /> Payment will be made at the respective contract unit and/or lump sum price for each <br /> item shown in the Agreement, installed and accepted , which price and payment shall <br /> constitute full compensation for furnishing all materials and performing all work in <br /> connection therewith and incidental thereto . Payments for partial completion of lump <br /> sum items shall be in accordance with ARTICLE 6 of the Agreement ( Section 00520 ) . All <br /> payments shall be subject to retainage withholding in accordance with said ARTICLE 6 . <br /> No separate payment will be made for the preparation of record drawings . <br /> 1 . 05 RESTORATION OF DAMAGED SURFACES , STRUCTURES AND PROPERTY <br /> Where pavement , trees , shrubbery , fences , or other property or surface structures not <br /> designated as pay items , or outside the limits of pay items , have been damaged , <br /> removed , or disturbed by the Contractor, whether deliberately or through failure to carry <br /> out the requirements of the Contract Documents , state laws , municipal ordinances , or <br /> the specific direction of the Engineer, or through failure to employ usual and reasonable <br /> safeguards , such property and surface structures shall be replaced or repaired at the <br /> expense of the Contractor to a condition equal to that before work began within a time <br /> frame approved by the Engineer. <br /> END OF SECTION <br /> IRC OPERATIONS COMPLEX 01025 — Measurement and Payment <br /> 01025-2 <br />