' performance of any authority or responsibility by of an adjustment in the Contract Price or Contract Times, or
<br /> ENGINEER shall create, impose, or give rise to any duty in both, that should be allowed as a result of a Work Change
<br /> contract, tort, or otherwise owed by ENGINEER to Directive, a Claim may be made therefor as provided in
<br /> ' CONTRACTOR, any Subcontractor, any Supplier, any paragraph 10 . 05 .
<br /> other individual or entity, or to any surety for or employee
<br /> or agent of any of them. 10 . 02 Unauthorized Changes in the Work
<br /> ' B . ENGINEER will not supervise, direct, control, or A. CONTRACTOR shall not be entitled to an
<br /> have authority over or be responsible for CONTRACTOR' s increase in the Contract Price or an extension of
<br /> the
<br /> means, methods, techniques, sequences, or procedures of Contract Times with respect to any work performed that is
<br /> construction, or the safety precautions and programs not required by the Contract Documents as amended,
<br /> incident thereto, or for any failure of CONTRACTOR to modified, or supplemented as provided in paragraph 3 .04,
<br /> comply with Laws and Regulations applicable to the perfor- except in the case of an emergency as provided in paragraph
<br /> ' mance of the Work. ENGINEER will not be responsible 6 . 16 or in the case of uncovering Work as provided
<br /> in
<br /> for CONTRACTOR' s failure to perform the Work in accor- paragraph 13 .04 .B .
<br /> dance with the Contract Documents.
<br /> 10 . 03 Execution of Change Orders
<br /> C. ENGINEER will not be responsible for the acts or
<br /> omissions of CONTRACTOR or of any Subcontractor, any A. OWNER and CONTRACTOR shall execute
<br /> Supplier, or of any other individual or entity performing appropriate Change Orders recommended by ENGINEER
<br /> any of the Work. (or Written Amendments) covering:
<br /> D . ENGINEER's review of the final Application for 1 . changes in the Work which are : (i)
<br /> Payment and accompanying documentation and all mainte- ordered by OWNER pursuant to paragraph 10.0l .A,
<br /> nance and operating instructions, schedules, guarantees, (ii) required because of acceptance of defective
<br /> Bonds, certificates of inspection, tests and approvals, and Work under paragraph 13 . 08 .A or OWNER' s
<br /> other documentation required to be delivered by paragraph correction of defective Work under paragraph 13 .09,
<br /> 14 . 07.A will only be to determine generally that their or (iii) agreed to by the parties;
<br /> content complies with the requirements of, and in the case
<br /> of certificates of inspections, tests, and approvals that the 2 . changes in the Contract Price or Contract
<br /> results certified indicate compliance with, the Contract Times which are agreed to by the parties, including
<br /> Documents. any undisputed sum or amount of time for Work
<br /> actually performed in accordance with a Work
<br /> E. The limitations upon authority and responsibility Change Directive; and
<br /> ' set forth in this paragraph 9. 10 shall also apply to
<br /> ENGINEER' s Consultants, Resident Project Repre- 3 . changes in the Contract Price or Contract
<br /> sentative, and assistants. Times which embody the substance of any written
<br /> decision rendered by ENGINEER pursuant to para-
<br /> ARTICLE 10 - CHANGES IN THE WORK; CLAIMS graph 10 .05 ; provided that, in lieu of executing any
<br /> such Change Order, an appeal may be taken from
<br /> ' any such decision in accordance with the provisions
<br /> 10 .01 Authorized Changes in the Work of the Contract Documents and applicable Laws and
<br /> Regulations, but during any such appeal,
<br /> A. Without invalidating the Agreement and without CONTRACTOR shall carry on the Work and adhere
<br /> ' notice to any surety, OWNER may, at any time or from time to the progress schedule as provided in paragraph
<br /> to time, order additions, deletions, or revisions in the Work 6. 18 .A.
<br /> by a Written Amendment, a Change Order, or a Work
<br /> ' Change Directive. Upon receipt of any such document, 10 . 04 Notification to Surety
<br /> CONTRACTOR shall promptly proceed with the Work
<br /> involved which will be performed under the applicable A. If notice of any change affecting the general scope
<br /> conditions of the Contract Documents (except as otherwise of the Work or the provisions of the Contract Documents
<br /> ' specifically provided). (including, but not limited to, Contract Price or Contract
<br /> Times) is required by the provisions of any Bond to be
<br /> B . If OWNER and CONTRACTOR are unable to given to a surety, the giving of any such notice will
<br /> be
<br /> ' agree on entitlement to, or on the amount or extent, if any, CONTRACTOR' s responsibility. The amount of each
<br /> ' 00700 - 31