a. claims have been made against OWNER Promptly thereafter, OWNER, CONTRACTOR, and <br /> on account of CONTRACTOR ' s performance or ENGINEER shall make an inspection of the Work to <br /> furnishing of the Work; determine the status of completion. If ENGINEER does not <br /> ' consider the Work substantially complete, ENGINEER will <br /> Part of Paragraph 14.02 .D.1 .2 .b. has been deleted . notify CONTRACTOR in writing giving the reasons <br /> b . Liens have been filed in connection with therefor. If ENGINEER considers the Work substantially <br /> the Work, eiieept ,. .he .e CONTRACTOR f TO h complete, ENGINEER will prepare and deliver to OWNER <br /> YY1116r <br /> deli. . 1{.r ed " ",.; f: ,, Bond satisf etei.. . to n" "`T a tentative certificate of Substantial Completion which shall <br /> ER to seeuEe the satin faetie;, and aicchar—gfix the date of Substantial Completion. There shall be <br /> sues; attached to the certificate a tentative list of items to be <br /> completed or corrected before final payment. OWNER <br /> c . there are other items entitling OWNER to shall have seven days after receipt of the tentative certificate <br /> a set-off against the amount recommended; or during which to make written objection to ENGINEER as <br /> to any provisions of the certificate or attached list. If, after <br /> d. OWNER has actual knowledge of the considering such objections, ENGINEER concludes that the <br /> occurrence of any of the events enumerated in Work is not substantially complete, ENGINEER will within <br /> paragraphs 14 .02 .B . 5 .a through 14 .02 .B . 5 .c or 14 days after submission of the tentative certificate <br /> to <br /> paragraph 15 .02 .A. OWNER notify CONTRACTOR in writing, stating the <br /> reasons therefor. If, after consideration of OWNER' s <br /> New paragraphs 14.02.D. 1 .e, f, and g have been added . objections, ENGINEER considers the Work substantially <br /> ' See the Supplementary Conditions. complete, ENGINEER will within said 14 days execute and <br /> deliver to OWNER and CONTRACTOR a definitive <br /> 2 . If OWNER refuses to make payment of certificate of Substantial Completion (with a revised <br /> ' the full amount recommended by ENGINEER, tentative list of items to be completed or corrected) <br /> OWNER must give CONTRACTOR immediate reflecting such changes from the tentative certificate as <br /> written notice (with a copy to ENGINEER) stating ENGINEER believes justified after consideration of any <br /> the reasons for such action and promptly pay CON- objections from OWNER. At the time of delivery of the <br /> TRACTOR any amount remaining after deduction tentative certificate of Substantial Completion ENGINEER <br /> of the amount so withheld. OWNER shall promptly will deliver to OWNER and CONTRACTOR a written <br /> pay CONTRACTOR the amount so withheld, or any recommendation as to division of responsibilities pending <br /> ' adjustment thereto agreed to by OWNER and final payment between OWNER and CONTRACTOR with <br /> CONTRACTOR, when CONTRACTOR corrects to respect to security, operation, safety, and protection of the <br /> OWNER' s satisfaction the reasons for such action. Work, maintenance, heat, utilities, insurance, and warranties <br /> ' and guarantees. Unless OWNER and CONTRACTOR <br /> 3 . If it is subsequently determined that agree otherwise in writing and so inform ENGINEER in <br /> OWNER's refusal of payment was not justified, the writing prior to ENGINEER' s issuing the definitive <br /> amount wrongfully withheld shall be treated as an certificate of Substantial Completion, ENGINEER' s <br /> ' amount due as determined by paragraph 14 . 02 . C. 1 . aforesaid recommendation will be binding on OWNER and <br /> CONTRACTOR until final payment. <br /> 14 . 03 CONTRACTOR 'S Warranty of Title <br /> ' B . OWNER shall have the right to exclude <br /> A. CONTRACTOR warrants and guarantees that title CONTRACTOR from the Site after the date of Substantial <br /> to all Work, materials, and equipment covered by any Completion, but OWNER shall allow CONTRACTOR <br /> Application for Payment, whether incorporated in the reasonable access to complete or correct <br /> items on the <br /> ' Project or not, will pass to OWNER no later than the time tentative list. <br /> of payment free and clear of all Liens . <br /> 14 . 05 Partial Utilization <br /> ' 14 . 04 Substantial Completion <br /> A. Use by OWNER at OWNER' s option of any <br /> A. When CONTRACTOR considers the entire Work substantially completed part of the Work which has <br /> ready for its intended use CONTRACTOR shall notify specifically been identified in the Contract Documents, or <br /> ' OWNER and ENGINEER in writing that the entire Work is which OWNER, ENGINEER, and CONTRACTOR agree <br /> substantially complete (except for items specifically listed constitutes a separately functioning and usable part of the <br /> by CONTRACTOR as incomplete) and request that Work that can be used by OWNER for its intended purpose <br /> ' ENGINEER issue a certificate of Substantial Completion. without significant interference with CONTRACTOR's <br /> ' 00700 - 41 <br />