Approval-Major and Minor Construction Changes, Form No. 70041047. <br /> 23 , TIME EXTENSIONS . <br /> The County may grant an extension of Contract Time when it add s new work items or provides for <br /> unforeseen work, provided that the additional work actually impacts the contract critical path completion <br /> schedule . The City may also ici atfo foreseeable atContract <br /> the time ofwhen <br /> bid or if failurretoflthe County to fulfill an <br /> yed <br /> by factors not reasonably anticipated or <br /> obligation under the contract results in delays to the schedule critical path . The County may consider the <br /> delays in delivery of materials or equipment that affect progress on a critical item of work as the basis for <br /> granting a time extension if such delays are beyond the control of the Contractor . Requests for time <br /> extensions due to delay in the delivery of custom <br /> do umentation that theforder was placedactured iolr fixtures will tconsidered be <br /> in timely manner and the lack of <br /> unless the contractor fu <br /> such equipment cased a delay in progress on a critical item . <br /> Extensions of Contract Time will not be granted for delays due to the fault or negligence of the <br /> Contractor. <br /> No allowance for inclement weather should be made in establishing the Contract Time . The County <br /> may grant time extensions on a day for day basis for delays caused only by inclement weather conditions that <br /> prevent the contractor from productively performing critical path items where : (i) the contractor jis unable to <br /> work at least 50 % of the day on a pre-determined critical path item due to the weather; or a ) the contractor <br /> must make major repairs to work damaged by weather provided that the damage is not due to the contractor's <br /> failure to perform and that the contractor is unable to work at least 50 % of the day on pre-determined critical <br /> path items . <br /> 24 . LIQUIDATED DAMAGES <br /> Applicable liquidated damages will be assessed in the following amount : $ 580 . 00 per day <br /> 25 . CONTRACT CLAIMS BY CONTRACTOR <br /> Should the contractor intend to file a claim for additional monetary compensation , time or other <br /> adjustments to the contract and the County disputes the contractor's entitlement to the claim or the impact of <br /> the claim , Contractor must provide written notification to the County of contractor' s intent to file a claim . This <br /> notice must be given before the contractor begins any work on which the claim is based . Failure of the <br /> contractor to notify the County before beginning work on any disputed items waives the contractor's right to <br /> claim . The contractor's notice of intent to file a claim should contain : <br /> ( 1 ) A statement as to what changed , including a description of the nature and extent of the <br /> change . <br /> (2) An indication of who directed or what caused the change . <br /> org <br /> (3) impactedion of how the tical activities on gthehas or will impact the contractor's latest accepted tschedule ' reference to any <br /> update <br /> P <br /> (4) A statement time and/or other adjustmentdamaes , or an estimate of tdo amages if )o he contract thats being <br />lr qung test count of <br /> compensationn ,, <br /> 26 . DRUG -FREE WORKPLACE CERTIFICATION <br /> In accordance with Florida Statute 287 . 0871 the bidder shall certify that it has and will maintain a drug-free <br /> workplace . The bidder shall complete and submit with its bid proposal the attached certification . Failure to <br /> include an executed certification may cause the bid proposal to be considered non-responsive . <br /> 23 <br /> F :\Engineering\Capital Projects\0216- 12th Street Between 16th Avenue and 11th Place\0216 Federal Contract <br /> provisions . doc <br /> 8/29/20083:06:25 PM <br />