L <br /> SECTION 00800 - SUPPLEMENTARY CONDITIONS TO THE <br /> GENERAL CONDITIONS <br /> SC-1 . 00 Introduction <br /> These Supplementary Conditions amend or supplement the Standard General Conditions of the <br /> Construction Contract (No . 1910-8 , 1996 Edition) and other provisions of the Contract <br /> r Documents as indicated below. All provisions , which are not so amended or supplemented , <br /> remain in full force and effect . <br /> The terms used in these Supplementary Conditions will have the meanings indicated in the <br /> General Conditions . <br /> SC-1 . 01 Defined Terms <br /> SC-1 All A. 20 Add the following language at the end of GC- 1 . 01 .A. 20 : <br /> ENGINEER'S CONSULTANT: Name William B . Zentz & Associates , Inc. <br /> Address 684 Old Dixie Highway <br /> City , State , Zip Vero Beach , Florida 32960 <br /> Phone (772) 567-7552 <br /> SC-2. 05 Before Starting Construction <br /> SC-2 . 05 . C . Delete paragraph GC 2. 05. 0 in its entirety and insert the following paragraph in its <br /> place: <br /> C . Evidence of Insurance: CONTRACTOR shall not commence work under this <br /> Contract until he has obtained all insurance required under Article 5 and such <br /> insurance has been delivered to the OWNER and approved by the OWNER, nor <br /> shall the CONTRACTOR allow any Subcontractor to commence work on his <br /> subcontract until all similar insurance required of the Subcontractor has been so <br /> obtained and approved . All such insurance shall remain in effect until final <br /> payment and at all times thereafter when CONTRACTOR may be correcting , <br /> removing or replacing defective Work in accordance with Article 13 . <br /> SC -2.06 Preconstruction Conference <br /> SC-2 . 06 Delete paragraph GC 2. 06.A in its entirety and insert the following paragraph in its <br /> place: <br /> A. Immediately after awarding the contract, but before the CONTRACTOR begins <br /> work, the Engineer will call a preconstruction conference at a place the <br /> ENGINEER designates to establish an understanding among the parties as to <br /> the work and to discuss schedules referred to in paragraph 2 . 05. 13, procedures <br /> for handling Shop Drawings and other submittals , and maintaining required <br /> records . Utility companies and others as appropriate will be requested to attend <br /> to discuss and coordinate work. <br /> SC-3.06 Coordination of Plans, Specifications, and Special Provisions <br /> SC4 . 06 Add the following new paragraphs immediately after paragraph GC-3. 05: <br /> SC-3 . 06 Coordination of Plans, Specifications, and Special Provisions <br /> A. In case of discrepancy, the governing order of the documents shall be as follows: <br /> 1 . Written Interpretations <br /> 00800-1 <br /> 00800 - Supplementary Conditions REV 04-07.doc <br /> 008001 FAEnginseringlSpectal ProjectsVEagle Trace Phase Mmtract Documents\Eagle Trace Subdivision Phase M0800 - Supplementary Conditions REV 0447.doc <br />