thereby; however, CONTRACTOR shall not be liable 2 . 07 Initial Acceptance of Schedules <br /> to OWNER or ENGINEER for failure to report any <br /> conflict , error , ambiguity, or discrepancy in the A. Unless otherwise provided in the Contract <br /> Contract Documents unless CONTRACTOR knew or Documents , at least ten days before submission of the <br /> reasonably should have known thereof. first Application for Payment a conference attended by <br /> CONTRACTOR , ENGINEER, and others as appropri- <br /> B . Preliminary Schedules: Within ten days after ate will be held to review for acceptability to ENGI <br />- <br /> the Effective Date of the Agreement ( unless otherwise NEER as provided below the schedules submitted in <br /> specified in the General Requirements ) , CONTRAC- accordance with paragraph 2 . 05 . 13 . CONTRACTOR <br /> TOR shall submit to ENGINEER for its timely review : shall have an additional ten days to make corrections <br /> and adjustments and to complete and resubmit the <br /> 1 . a preliminary progress schedule schedules . No progress payment shall be made to <br /> indicating the times ( numbers of days or dates ) CONTRACTOR until acceptable schedules are <br /> for starting and completing the various stages submitted to ENGINEER . <br /> of the Work, including any Milestones specified <br /> in the Contract Documents ; 1 . The progress schedule will be <br /> acceptable to ENGINEER if it provides an <br /> 2 . a preliminary schedule of Shop orderly progression of the Work to completion <br /> Drawing and Sample submittals which will list within any specified Milestones and the <br /> each required submittal and the times for sub- Contract Times . Such acceptance will not <br /> mitting , reviewing , and processing such impose on ENGINEER responsibility for the <br /> submittal ; and progress schedule , for sequencing , scheduling , <br /> or progress of the Work nor interfere with or <br /> 3 . a preliminary schedule of values for relieve CONTRACTOR from CONTRACTOR' s <br /> all of the Work which includes quantities and full responsibility therefor. <br /> prices of items which when added together <br /> equal the Contract Price and subdivides the 2 . CONTRACTOR' s schedule of Shop <br /> Work into component parts in sufficient detail to Drawing and Sample submittals will be <br /> serve as the basis for progress payments acceptable to ENGINEER if it provides a <br /> during performance of the Work . Such prices workable arrangement for reviewing and <br /> will include an appropriate amount of overhead processing the required submittals . <br /> and profit applicable to each item of Work . <br /> 3 . CONTRACTOR ' s schedule of values <br /> G--�Eepseof a8e#sre -any aAle will be acceptable to ENGINEER as to form <br /> the Site is started , CONTRACTOR and OWNE all and substance if it provides a reasonable <br /> each deliver to the other , with cop,1P.1 o each allocation of the Contract Price to component <br /> additional insured identified in t upplementary parts of the Work . <br /> Conditions , certificates of urance (and other ARTICLE 3 - CONTRACT DOCUMENTS : INTENT , <br /> evidence of insurance Ich either of them or any AMENDING , REUSE <br /> additional insur may reasonably request) which <br /> CONTRA and OWNER respectively are <br /> serdaase-W4h 3 . 01 Intent <br /> ' ste-a . <br /> A. The Contract Documents are comple- <br /> 2 . 06 Preconstruction Conference mentary; what is called for by one is as binding as if <br /> called for by all . <br /> to run , but before any Work at the Site i a.rted , a B . It is the intent of the Contract Documents <br /> to <br /> conference attended by CONTRAC ENGINEER, describe a functionally complete Project (or part there- <br /> and others as appropriate w' held to establish a of) to be constructed in accordance with the Contract <br /> working understandin ong the parties as to the Documents . Any labor , documentation , services , <br /> Work and to di s the schedules referred to in para- materials , or equipment that may reasonably be <br /> graph 2 . 0 , procedures for handling Shop Drawings inferred from the Contract Documents or from <br /> an er submittals , processing Applications for prevailing custom or trade usage as being required to <br /> GFdS . produce the intended result will be provided whether <br /> or not specifically called for at no additional cost to <br /> OWNER . <br /> 00700 - General Conditions REV 04-07.doc <br /> 00700 - 9 <br /> F:\Engineering\Special Projects\Eagle Trace Phase 2\Contract Documents\Eagle Trace Subdivision Phase II\00700 - General Conditions REV 04-07.dx <br />