2 .2 .4 Brine Main <br /> Pine in Trenches <br /> All pipe shall be laid to the depth and grades according to the Plans . The depth shall <br /> be <br /> measured from the established bench marks. <br /> Pipe Joints <br /> The ends of pipe, coupling grooves, gaskets and rubber rings shall be cleaned immediately before <br /> assembling. The assembly shall be made as recommended by the manufacturer. Lubricant for <br /> sealing gasket shall be as specified in ANSI 21 . 11 (AWWA C111 -72). Pipe shall not be <br /> deflected either vertically or horizontally in excess of that recommended by the manufacturer. <br /> Preventing Trench Water from Entering Pipe <br /> When pipe laying is not in progress, the open ends of installed pipe shall be closed by approved <br /> means to prevent entrance of trench water into the line. <br /> Floating Pipe <br /> ' Whenever water is excluded from the interior of the pipe, adequate backfill shall be placed on the <br /> pipe or well pointing installed to prevent floating. Any pipe which has floated shall be removed <br /> from the trench and be re-laid as directed by the Engineer. <br /> ' All foreignmatter or dirt shall be removed from the interior of i before lowering into position <br /> pipe <br /> in the trench. Pipe shall be kept clean by means approved by the Engineer during and after <br /> I <br /> aying. <br /> Alignment and Grade <br /> The pipe shall be laid, as directed by the Engineer, on a firm soil cut true and even to afford <br /> bearing for the full length of the barrel of the pipe. <br /> Temporary support, adequate protection and maintenance of all underground and surface utility <br /> ' structures, drains, sewers, and other obstructions encountered in the progress of the work shall be <br /> furnished by the Contractor at his own expense under the direction of the Engineer. <br /> Unsuitable Conditions for Joining Pipe <br /> No pipe shall be laid in wet trench conditions which preclude proper bedding, or on frozen trench <br /> J bottom, or when in the opinion of the Engineer the trench conditions or the weather are <br /> unsuitable for proper installation. <br /> J <br /> J <br /> 14 <br /> responsibilities associated with the furnishing or an ianor, matentuJ, vgLupiii%.=aL u.=. . ___• _ •• __-»-� <br /> required to install, complete, required trenchless installation of pressure mains, as shown on the <br /> Drawings and as specified herein. <br /> Experience <br /> The Contractor must demonstrate expertise in trenchless methods using a wire guided locating <br /> system by providing a list of ten ( 10) utility references for which similar work has been <br /> performed in the last two years. The references should include a name and telephone number <br /> where contact can be made to verify the contractor's capability. The Contractor must provide <br /> documentation showing successful completion of the projects used for reference. Conventional <br /> trenching experience will not be considered applicable. <br /> All supervisory personnel must be adequately trained and shall have at least four (4) years <br /> experience in directional boring. The Contractor shall submit the names and resumes of all <br /> supervisory field personnel prior to construction. <br /> Because of time constraints, the Contractor may wish to provide multiple experienced directional <br /> boring crews. <br /> The directional boring equipment shall be capable of installing the minimum pipe diameter noted <br /> on the plans. <br /> Submittals <br /> Submit technical data forui ment including clay slurry material, method of installation with <br /> �I P <br /> working drawings, and proposed sequence of construction for approval by the Engineer. <br /> I <br /> Prior to approval for directional boring, the Contractor must submit the names of supervisory <br /> field personnel and historical information of directional boring experience. In addition, the <br /> Contractor must submit for approval nameplate, data for the drilling equipment, mobile spoils <br /> removal unit, and MSDS (Material Safety Data Sheets) information for the drilling slurry <br /> compounds. <br /> The Contractor is required to bring to the attention of the Engineer any known design <br /> discrepancies with actual tunneling methods that the Contractor will be performing. This shall <br /> be stated in writing to the Engineer no later than the pre-construction meeting. <br /> Provide shop drawing submittal and sample of pipe, fused joint, and trace wire. <br /> 20 <br />