Laserfiche WebLink
ARTICLE 3, CONTRACT TIME . <br /> 3 . 1 The work will be completed in accordance with the following time frame . <br /> (a) Within 15 calendar days from effective date of Notice to Proceed , Contractor <br /> shall complete the following tasks : <br /> 1 . Obtain all necessary permits . <br /> ' 2 . Receive approved shop drawings for all materials and equipment to be <br /> utilized in the job . <br /> 3 . Perform all photographic recording and documentation of conditions <br /> ' prior to construction . <br /> 4 . Locate all existing utilities in the area of work. <br /> 5 . Mobilize all labor, equipment, and materials . <br /> 6 . Deliver and store all equipment and materials to the job site . <br /> 7 . Notify all utilities and other affected parties prior to initiating construction . <br /> ' (b) From 16 calendar days to 100 calendar days from the effective date of Notice to <br /> Proceed , the CONTRACTOR shall complete the following tasks : <br /> 1 . Install all pipe and appurtenant items . <br /> 2 . Perform all testing . <br /> 3 . Restore all disturbed areas to their pre-construction condition . <br /> ' 4 . Correct all deficiencies noted by Engineer. <br /> Completion of all tasks outlined above (i . e . , Subparagraphs a and b) constitute <br /> ' Substantial Completion . <br /> (c) From 101 calendar days to 120 calendar days from the effective date of Notice <br /> ' to Proceed , the CONTRACTOR shall complete the following tasks : <br /> 1 . Clean up project area . <br /> 2 . Remove all equipment and material from project site . <br /> 3 . Perform contract close-out procedures . <br /> Completion of all tasks outlined above (i . e . , Subparagraphs a , b , and c) constitute Final <br /> Completion . <br /> ' 3 . 2 Liquidated Damages . OWNER and CONTRACTOR recognize that time is of the <br /> essence of this Agreement and that OWNER will suffer financial loss if the work is not <br /> completed within the times specified in Paragraph 3 . 1 above, plus any extensions thereof <br /> allowed in accordance with Article 12 of the General Conditions . They also recognize the <br /> delays, expense and difficulties involved in proving in a legal proceeding the actual loss <br /> suffered by OWNER if the work is not completed on time. Accordingly, instead of requiring <br /> any such proof, OWNER and CONTRACTOR agree that as liquidated damages for delay <br /> 00530-2 <br /> F :1Utilities\UTILITY - ENGINEERINGTrojects - Utility Construction Permits\North County R . O. Brine Disposal Relocation100530 EJCDC <br /> ' - Agreement between Owner and Contractor-Tri Sure.doc <br />