A : <br /> Document G701T"y Mon <br /> AIA - 2001 <br /> Change Order <br /> PROJECT (Name and address): CHANGE ORDER NUMBER: 028 _ OWNER: <br /> New County Administration Building DATE: May 1, 2007 <br /> Lying Between the Main Relief Canal to ARCHITECT: <br /> the North, the Lateral D Canal on the CONTRACTOR: <br /> Sounth and East and 20th Avenue to the <br /> West FIELD: ❑ <br /> TO CONTRACTOR (Name and address): ARCHITECT'S PROJECT NUMBER: 2102 OTHER: ❑ <br /> Turner Construction Company CONTRACT DATE: (Amendment # 2) August 23, 2005 <br /> 800 N. Magnolia Avenue CONTRACT FOR: Guaranteed Maximum Price - <br /> Orlando, Florida 32803 Construction Manager at Risk <br /> THE CONTRACT IS CHANGED AS FOLLOWS: <br /> (Include, where applicable, any undisputed amount attributable to previously executed Construction Change Directives) <br /> CHANGE IN SCOPE: <br /> L Expand paving services to include the curbing and resurfacing of the Health Department Parking lot with <br /> same quality of asphalt as was specified for the new parking lot of the New County Administration Building <br /> for a not to exceed cost of: $70,000.00 <br /> 2. Repaint the existing Health Department Building including any need caulking or patching based on painting <br /> specifications for New County Administration Building for a not to exceed cost of: $ 15,000.00 <br /> Approval of these two Changes in Scope in this Change Order will not change the GMP or the Owners Contingency <br /> PCO Description Impact to GMP Tax Savings <br /> 927.4. 1 Ref. Owner Purchase Order #44590-00 (COR-106) JD Thornton <br /> Void Original Owner Purchase Order Return Purchase Amount to GMP $35, 175 <br /> Deduct original Tax Savings from Owner Contingency. ($2, 161 ) <br /> 927.8 Ref. Owner Purchase Order #44893-00 (COR- 107) Skinner Nurseries ($ 39, 195) $2,402 <br /> 928. 1 Ref. Owner Purchase Order #44751 -00 (COR-105) Images Graphics ($ 24,632) $ 1 ,528 <br /> Totals ($28,652) $ 1 ,769 <br /> Approval of this Change Order will decrease the GMP by $28,652and will decrease the Owner's Contingency by $ 1 ,769. <br /> The original Guaranteed Maximum Price was $ 33,086,442.00 <br /> The net change by previously authorized Change Orders $ (5,233,826.00) <br /> The Guaranteed Maximum Price prior to this Change Order was $ 27,852,616.00 <br /> The Guaranteed Maximum Price will be changed by this Change Order in the amount of $ ($28,652.00) <br /> The new Guaranteed Maximum Price including this Change Order will be $ 27,823,964.00 <br /> The Contract Time will be increased/decreased by zero ( 0 ) days. <br /> The date of Substantial Completion as of the date of this Change Order therefore is June 30, 2007 . <br /> NOTE: This Change Order does not include changes in the Contract Sum, Contract Time or Guaranteed Maximum Price which <br /> have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the Owner and <br /> Contractor, in which case a Change Order is executed to supersede the Construction Change Directive. <br /> AIA Document G701M — 2001 . Copyright ® 1979, 1987, 2000 and 2001 by The American Institute of Architects. All rights reserved. WARNING : This A€�." <br /> Document €s Protected by U.H. Ccpyrught Law and int,mationaI TreaBes. €lnnuallilzed reproduction 02 distribution a' this AIADocument. or any .) <br /> portion of L, may result in severe aihi and criminal penalcm and will be prasecured to Pte maximum extend pcsziWe emder thx law. This document <br /> was produced by AIA software at 19:24:11 on 04/24/2007 under Order No.1000250302 1 which expires on 7/25/2007, and is not for resale. <br /> User Notes: <br /> (1881882016) <br />