property insurance shall not be canceled or permitted to
<br /> lapse on account of any such partial use or occupancy. New Paragraphs 6.02MA9 29 39 49 59 6, and 7 have been
<br /> added. See the Supplementary Conditions.
<br /> ARTICLE 6 - CONTRACTOR' S RESPONSIBILITIES 6.03 Services, Materials, and Equipment
<br /> A. Unless otherwise specified in the General Re-
<br /> 6 . 01 Supervision and Superintendence quirements, CONTRACTOR shall provide and assume full
<br /> responsibility for all services, materials, equipment, labor,
<br /> A. CONTRACTOR shall supervise, inspect, and transportation, construction equipment and machinery,
<br /> direct the Work competently and efficiently, devoting such tools, appliances, fuel, power, light, heat, telephone, water,
<br /> attention thereto and applying such skills and expertise as sanitary facilities, temporary facilities, and all other
<br /> may be necessary to perform the Work in accordance with facilities and incidentals necessary for the performance,
<br /> the Contract Documents. CONTRACTOR shall be solely testing, start-up, and completion of the Work.
<br /> responsible for the means, methods, techniques, sequences,
<br /> and procedures of construction, but CONTRACTOR shall B . All materials and equipment incorporated into the
<br /> not be responsible for the negligence of OWNER or Work shall be as specified or, if not specified, shall
<br /> be of
<br /> ENGINEER in the design or specification of a specific good quality and new, except as otherwise provided in the
<br /> means, method, technique, sequence, or procedure of Contract Documents. All warranties and guarantees
<br /> construction which is shown or indicated in and expressly specifically called for by the Specifications shall expressly
<br /> required by the Contract Documents. CONTRACTOR run to the benefit of OWNER. If required by ENGINEER,
<br /> shall be responsible to see that the completed Work CONTRACTOR shall famish satisfactory evidence
<br /> complies accurately with the Contract Documents. (including reports of required tests) as to the source, kind,
<br /> and quality of materials and equipment. All materials and
<br /> B . At all times during the progress of the Work, equipment shall be stored, applied, installed,
<br />connected,
<br /> CONTRACTOR shall assign a competent resident superin- erected, protected, used, cleaned, and conditioned in
<br /> tendent thereto who shall not be replaced without written accordance with instructions of the applicable Supplier,
<br /> notice to OWNER and ENGINEER except under except as otherwise may be provided in the Contract Docu-
<br /> extraordinary circumstances. The superintendent will be ments.
<br /> CONTRACTOR' s representative at the Site and shall have
<br /> authority to act on behalf of CONTRACTOR. All 6.04 Progress Schedule
<br /> communications given to or received from the superin-
<br /> tendent shall be binding on CONTRACTOR. A. CONTRACTOR shall adhere to the progress
<br /> schedule established in accordance with paragraph 2 .07 as it
<br /> 6 .02 Labor; Working Hours may be adjusted from time to time as provided below.
<br /> A. CONTRACTOR shall provide competent, suitably 1 . CONTRACTOR shall submit to ENGI-
<br /> qualified personnel to survey, lay out, and construct the NEER for acceptance (to the extent indicated
<br /> in
<br /> Work as required by the Contract Documents. CON- paragraph 2 .07) proposed adjustments in the prog-
<br /> TRACTOR shall at all times maintain good discipline and ress schedule that will not result in changing the
<br /> order at the Site. Contract Times (or Milestones) . Such adjustments
<br /> will conform generally to the progress schedule then
<br /> B . Except as otherwise required for the safety or in effect and additionally will comply with
<br /> any
<br /> protection of persons or the Work or property at the Site or provisions of the General Requirements applicable
<br /> adjacent thereto, and except as otherwise stated in the thereto. '
<br /> Contract Documents, all Work at the Site shall be
<br /> performed during regular working hours, and CON- 2. Proposed adjustments in the progress
<br /> TRACTOR will not permit overtime work or the schedule that will change the Contract Times (or
<br /> performance of Work on Saturday, Sunday, or any legal Milestones) shall be submitted in accordance with
<br /> holiday without OWNER' s written consent (which will not the requirements of Article 12 . Such adjustments
<br /> be unreasonably withheld) given after prior written notice to may only be made by a Change Order or Written
<br /> ENGINEER. Amendment in accordance with Article 12 .
<br /> 6.05 Substitutes and "Or-Equals "
<br /> Rev . 03 / 2006 Egret Marsh
<br /> 00700 - 20