Laserfiche WebLink
Item 1 - Response to RFI received subsequent to the issuance of ADDENDUM #3 : <br /> 1 . ARE THE SIDEWALKS AND PARKING LOTS FOR BOPPY' S AND THE REAL ESTATE GOING <br /> TO STAY , AS IS , OR ARE THEY COMING OUT? <br /> The sidewalks are to stay as is, and CONTRACTOR will be responsible for making a smooth <br /> transition from the parking lot and sidewalk apron to the existing sidewalk. <br /> 2 . SUPPLEMENTARY CONDITION 17 . 14 — MINIMUM PERCENTAGE OF WORK TO BE <br /> PERFORMED BY CONTRACTOR - STATES THE CONTRACTOR MUST PERFORM AT LEAST <br /> 51 % OF THE WORK WITH ITS OWN PERSONNEL AND EQUIPMENT , PLEASE PROVIDE <br /> CLARIFICATION OF THE INTENT OF THE OWNER AS WE WOULD BE UNABLE TO ADHERE <br /> TO THIS CONDITION , BUT WOULD LIKE TO BID THE PROJECT AND HAVE BEEN WORKING <br /> FEVERISHLY TO ASSEMBLE OUR PROPOSAL . <br /> In the CONDITIONS OF THE CONTRACT, Section 00800 Supplementary Conditions to the General <br /> Conditions, Article SC47. 14 Minimum Percentage of Work to be Performed by CONTRACTOR, <br /> DELETE THAT ARTICLE. <br /> 3 . THE FOLLOWING WAS RECEIVED FROM A BIDDER ; " I SPOKE WITH CATHY KEMP THIS <br /> AFTERNOON . ( 772-489-6254 ) SHE IS THE SERVICE PLANNER FOR FPL FOR THIS SITE . <br /> SHE INDICATED THEFOLLOWING : <br /> THERE IS NO 3 PHASE POWER ON THE POLES ON THE NORTH SIDE OF THE PROPERTY . <br /> THE ONLY WAY TO GET 3 PHASE TO THE NW CORNER IS TO COME ACROSS SR A1A, <br /> WHICH WOULD REQUIRE DOT PERMIT , LENGTHY PROCESS , ACCORDING TO CATHY . <br /> AN OPTION FOR LIFT STATION 3 PHASE WOULD BE TO COME FROM THE CONCRETE <br /> POLE NEXT TO THE SIDEWALK BETWEEN BOPPY ' S AND THE REALESTATE OFFICE . SHE <br /> SAID FEES WOULD BE REQUIRED FOR THE TRANSFORMERS AND LABOR . HOW MUCH : <br /> SHE DIDN 'T KNOW . ANOTHER QUESTION FROM MY END WOULD BE , CAN WE RUN <br /> UNDERGROUND THRU THE REAL ESTATE PARKING LOT?" <br /> I j <br /> FPL has already been requested to extend 3-phase power to the power pole shown on the plans, <br /> see sheet U- 8a and the attached service request. It should also be noted that there is no platted <br /> easement between lots 4 and 5 (Boppy's and the Office building), nor do we have any authorization <br /> to install utilities through the private parking lot. <br /> FAPublic Works\Cliff Suthard\Wabasso Beach Park\A Construction Bid Documents\Bid Documents as of 2-6-2008\Addendum #1 #2 , #3 , #4 , & <br /> #5\Addendum #4.doc <br /> Page 2 of 2 <br />