PART 3 - EXECUTION <br /> 3 .01 Foundations <br /> The standard foundation for pre-cast manholes shall be as follows : <br /> A. Undisturbed, existing in-place, natural granular soils consisting which have been finished <br /> graded by hand to final elevation. No over excavation shall be permitted. <br /> B . For manholes not placed on undisturbed, existing, in-place natural granular soils, a 12 <br /> inch layer of 3/8 " to 3/4" crushed rock shall be placed on the prepared trench bottom, and <br /> compacted. A two inch layer of high early strength cement grout may be placed on top of <br /> the rock base for leveling. The manhole base shall be set on the foundation, to the proper <br /> invert elevation, while the grout is still workable, so that the grout will fill all voids <br /> beneath the manhole base. <br /> 3 .02 Manholes <br /> All workmanship shall conform to best standard practice. Manholes shall be built accurately to the <br /> dimensions shown on the Plans . The top of the manholes shall be brought accurately to grade with <br /> masonry. <br /> Manholes shall be completed (with inverts, frames and covers) as the work progresses. <br /> Particular care shall be taken that no water rises on the masonry until the mortar is thoroughly set. <br /> Any masonry damaged in this manner shall be removed upon the order of the Engineer. H <br /> All pipes or castings to be embedded in masonry work shall be accurately set and if so required, <br /> headers shall be laid around the casting so embedded. Spurs and stubs for branch lines shall be built <br /> in the manholes where shown on the Plans or otherwise required by the Engineer. They shall be <br /> closed with vitrified plugs. <br /> 3 .03 Watertight Workmanship <br /> The entire work of constructing manholes must be carried on in a manner to insure watertight work. <br /> Any leaks in manholes shall be caulked, repaired or the entire work shall be removed and rebuilt. <br /> a <br /> 3 .04 Disposal of Water from Excavations rrf <br /> All water pumped or bailed from excavations shall be conveyed in a proper manner to a suitable <br /> point of discharge by the Contractor at his own expense . <br /> �r <br /> The Contractor shall provide for the disposal of water removed from excavations in a manner that <br /> will not cause injury to public health, private or public property, any portion of the work completed <br /> or in progress, the surface of the streets, or cause any impediments to the reasonable use of the site <br /> by other Contractors. The Contractor shall be responsible for complying with all the local <br /> regulations of the Department of Environmental Regulation regarding pollution of the canals. The <br /> Contractor shall take special precautions to eliminate any odor problems resulting from the <br /> discharge of sulfide water, such as submerged discharge outlets and overflow basins . <br /> 02531 — Gravity Sewer Manholes <br /> 02531 - 3 <br /> ■ <br />