Laserfiche WebLink
a. for costs incurred under paragraphs A. The Contract Times (or Milestones) will not be <br /> 11 .01 .A. 1 and 11 .01I .A. 2, the CONTRACTOR's fee extended due to delays within the control of CONTRACTOR. <br /> shall be 15 percent; Delays attributable to and within the control of a Subcontractor <br /> ' or Supplier shall be deemed to be delays within the control of <br /> b. for costs incurred under paragraph CONTRACTOR. <br /> 11 .01 .A. 3, the CONTRACTOR's fee shall be five <br /> percent; 12.05 Delays Beyond OWNER's and CONTRACTOR's <br /> ' Control <br /> c. where one or more tiers of subcontracts <br /> are on the basis of Cost of the Work plus a fee and A. Where CONTRACTOR is prevented from completing <br /> no fixed fee is agreed upon, the intent of paragraph any part of the Work within the Contract Times (or Milestones) <br /> ' 12.01 .C.2. a is that the Subcontractor who actually due to delay beyond the control of both <br /> OWNER and <br /> performs the Work, at whatever tier, will be paid a CONTRACTOR, an extension of the Contract Times <br /> (or <br /> fee of 15 percent of the costs incurred by such Milestones) in an amount equal to the time lost <br /> due to such <br /> Subcontractor under paragraphs 11 .01 .A. 1 and delay shall be CONTRACTOR's sole and exclusive remedy for <br /> ' 11 .01 .A.2 and that any higher tier Subcontractor such delay. <br /> and CONTRACTOR will each be paid a fee of five <br /> percent of the amount paid to the next lower tier 12. 06 Delay Damages <br /> Subcontractor, <br /> A. In no event shall OWNER or ENGINEER be liable to <br /> d. no fee shall be payable on the basis of CONTRACTOR, any Subcontractor, any Supplier, or any other <br /> costs itemized under paragraphs 11 .01 .A.4, person or organization, or to any surety for or employee or <br /> I1 .01 .A.5, and 11 .013; agent of any of them, for damages arising out of or resulting <br /> ' from: <br /> e. the amount of credit to be allowed by <br /> CONTRACTOR to OWNER for any change which 1 . delays caused by or within the control of CON- <br /> results in a net decrease in cost will be the amount TRACTOR; or <br /> of the actual net decrease in cost plus a deduction <br /> in CONTRACTOR's fee by an amount equal to five 2. delays beyond the control of both OWNER and <br /> percent of such net decrease; and CONTRACTOR including but not limited to fires , floods, <br /> epidemics , abnormal weather conditions, acts of God, <br /> f. when both additions and credits are in- or acts or neglect by utility owners or other contractors <br /> ' volved in any one change, the adjustment in performing other work as contemplated by Article 7. <br /> CONTRACTOR's fee shall be computed on the <br /> basis of the net change in accordance with para- B. Nothing in this paragraph 12.06 bars a change in <br /> graphs 12.01 .C.2.a through 12.01 .C.2.e, inclusive. Contract Price pursuant to this Article 12 to compensate <br /> ' CONTRACTOR due to delay, interference, or disruption directly <br /> 12.02 Change of Contract Times attributable to actions or inactions of OWNER or anyone for <br /> A. The Contract Times (or Milestones) may only be whom OWNER is responsible. <br /> changed by a Change Order or by a Written Amendment. Any <br /> Claim for an adjustment in the Contract Times (or Milestones) ARTICLE 13 - TESTS AND INSPECTIONS; CORRECTION, <br /> shall be based on written notice submitted by the party making REMOVAL OR ACCEPTANCE OF DEFECTIVE WORK <br /> the claim to the ENGINEER and the other party to the Contract <br /> ' in accordance with the provisions of paragraph 10.05. <br /> B. Any adjustment of the Contract Times (or Milestones) 13. 01 Notice of Defects <br /> covered by a Change Order or of any Claim for an adjustment in A. Prompt notice of all defective Work of which OWNER <br /> ' the Contract Times (or Milestones) will be determined in or ENGINEER has actual knowledge will be given to <br /> accordance with the provisions of this Article 12. CONTRACTOR. All defective Work may be rejected, corrected, <br /> 12.03 Delays Beyond CONTRACTOR's Control or accepted as provided in this Article 13. <br /> ' A. Where CONTRACTOR is prevented from completing 13.02 Access to Work <br /> any part of the Work within the Contract Times (or Milestones) A. OWNER, ENGINEER, ENGINEER's Consultants, <br /> due to delay beyond the control of CONTRACTOR, the Contract other representatives and personnel of OWNER, independent <br /> Times (or Milestones) will be extended in an amount equal to testing laboratories, and governmental agencies with <br /> the time lost due to such delay if a Claim is made therefore as jurisdictional interests will have access to the Site and <br />the Work <br /> provided in paragraph 12.02.A. Delays beyond the control of at reasonable times for their observation, inspecting, <br /> and <br /> CONTRACTOR shall include, but not be limited to, acts or testing. CONTRACTOR shall provide them proper and <br /> safe <br /> ' neglect by OWNER, acts or neglect of utility owners or other conditions for such access and advise them <br /> of <br /> contractors performing other work as contemplated by Article 7, CONTRACTOR's Site safety procedures and programs so that <br /> fires, floods, epidemics, abnormal weather conditions, or acts of they may comply therewith as applicable. <br /> God. <br /> ' <br /> 12.04 Delays Within CONTRACTOR'S Control 13. 03 Tests and Inspections <br /> A_ CONTRACTOR shall give ENGINEER timely notice of <br /> readiness of the Work for all required inspections , tests, or <br /> ' 6706-38392\8/20/03 00700-27 V)2B <br />