Laserfiche WebLink
ATTACHMENT C <br /> PROJECT SCHEDULE <br /> INDIAN RIVER COUNTY SOLID WASTE DISPOSAL DISTRICT <br /> ENGINEERING SERVICES FOR <br /> SECOND LATERAL C&D CELL EXPANSION - 2004-2005 <br /> PROTECT SCHEDULE <br /> Prepare Permit Renewal for C&D Operations Permit 1 Month from Notice to Proceed <br /> Prepare Design Plans and Drawing 1 Month from Notice to Proceed <br /> Prepare Permit Modifications and Receive Permit Approval 1 Month from Preparation of Plans <br /> Bidding Services Approximately 45 Days <br /> (30 days bidding and 15 days evaluation and recommendation to Award) <br /> Construction Period Approximately 60 Days <br /> C-1 mh1870. doc <br />