CONCEPTUAL CONSTRUCTION COST ESTIMATE
<br /> BIOSOLIDS DEWATERING FACILITY AT THE IRC LANDFILL
<br /> Unit Capital Operations
<br /> Price Units Cost / Price Cost / Price
<br /> Site Work $75,000 LS $ 75, 000
<br /> Grease and Septage Offloading Area (2) $15,000 2 $30, 000
<br /> Grease and Septage degritting and deragging
<br /> (Communiter and Pumps) $22,000 3 $66,000
<br /> IRC Tanker truck offloading area $15,000 1 $15,000
<br /> Three 100kga1 sludge storage tanks Glass Lined Steel
<br /> (GLS) w/ dome lid $135, 000 3 $405,000
<br /> Mixers for sludge storage tanks $4,500 6 $27,000
<br /> Odor Control for Storage Tanks (Biocube or Ozone
<br /> Headspace) $150,000 1 $150,000
<br /> Sludge Transfer Pumps to Centrifuge $14,000 3 $42,000
<br /> Centrifuges (2) $392,000 2 $784, 000
<br /> Centrate Ground Storage Tank Bolted Steel (0 . 5 Mgal)
<br /> GLS w/ dome $260, 000 1 $260,000
<br /> Cake Conveyor to Sludge Loadout area $100,000 1 $100,000
<br /> Centrate / Wastewater Lift Station / FM to 74th Ave . $80,000 1 $80,000
<br /> Generator for Class I reliability $275,000 1 $275,000
<br /> Miscellaneous $125,000 1 $125, 000
<br /> Yard Piping $80, 000 1 $80, 000
<br /> MCC room, Small Laboratory, Bathroom with Shower $65, 000 1 $65,000
<br /> Chemical Tank and Pump Skid for Phosphorus
<br /> Removal $45,000 1 $45,000
<br /> Subtotal $1 , 740,000 $884,000
<br /> Instrumentation (10 % ) $174,000 $88,400
<br /> Electrical (15 % ) $261 , 000 $132,600
<br /> Subtotal $2, 175 , 000 $1 ,105 ,000
<br /> Contingency (15 % ) $326,250 $165 , 750
<br /> Total Estimated Construction Cost $2,501250 $1 , 270 ,750
<br /> A-11 mh2200. doc