ATTACHMENT C <br /> SCHEDULE <br /> WORK ORDER NUMBER 2 <br /> BIOSOLIDS DEWATERING AT THE INDIAN RIVER COUNTY LANDFILL <br /> Milestone Duration <br /> Preliminary Design Report 1 . 5 Months 45 days <br /> Site Plan Permitting 4 Months 120 days <br /> Final Design 5 . 5 Months 165 days <br /> Bidding 1 . 5 Months 45 days <br /> Operations Procurement 1 . 5 Months 45 days <br /> Construction Complete 8 Months 240 days <br /> Total Time 15 Months 450 days <br /> C-1 mh2200.doc <br />