approved plans including coordination with IRC SWDD scheduling, water level measurements,
<br /> data review and analysis, and reporting . In addition, CDM will install two staff gauges in the
<br /> C-5 canal and two staff gauges in the Lateral C canal once the permit has been received from the
<br /> Indian River Farms Water Control District (IRFWCD ) . CDM will contract a surveyor to survey
<br /> the surface water sample locations and proposed staff gauges once installed . CDM will contract
<br /> with Ideal Tech Service Inc . (ITS) to perform the groundwater and surface water sampling .
<br /> CDM/ ITS will perform the 2011 quarterly (January, April, July, and October) sampling of
<br /> seven groundwater monitoring wells ( MW4S, MW-2S, MW-3S, MW-13S, MW-C1 , MW-C2 and
<br /> MW- C3) for analysis of iron, chlorides, TDS, sodium, ammonia, nickel, arsenic, silver, thallium,
<br /> hardness, BODS, COD, total nitrogen, and total phosphate . CDM / ITS will collect water level
<br /> data for the groundwater monitor wells and staff gauges immediately prior to the sampling
<br /> event. CDM/ ITS will also perform 2011 quarterly (January, April, July, and October) sampling
<br /> of six (6) surface water sites ( C5-SW1 , C5-SW2, C5-SW3, C5-SW6, LC-SW4, and LC-SW5) for
<br /> analysis of iron, chlorides, TDS, sodium, ammonia, nickel, arsenic, silver, thallium, hardness,
<br /> BODS, COD, total nitrogen, total phosphates, unionized ammonia, and chlorophyll A . It is
<br /> estimated that each monitoring event will take two days in the field to complete . In the event
<br /> that FDEP requires re-sampling of groundwater monitoring wells or surface water sites, or if an
<br /> algae bloom is observed and algal speciation sampling and analysis are required , the services
<br /> performed will be invoiced under Task 4 of this Scope of Services . CDM / ITS will deliver the
<br /> samples to the ENCO Orlando office for analysis . Laboratory analysis is not included in this
<br /> task .
<br /> ENCO will perform the laboratory analysis under IRC SWDD' s contract. CDM will assist IRC
<br /> SWDD in coordinating the analytical testing activities with ENCO, notify FDEP prior to
<br /> sampling as required and review and evaluate the analytical test results . The results of the
<br /> contamination evaluation monitoring will be reported with the semi- annual water quality
<br /> reports . This task includes attending one meeting with IRFWCD in Vero Beach and one meeting
<br /> with the Florida Department of Environmental Protection in Orlando . CDM reserves the right
<br /> to request additional compensation should additional meetings be required .
<br /> PROJECT SCHEDULE
<br /> The following project schedule has been developed based on authorization on January 4, 2011 .
<br /> Task 1 : January 1 , 2011 through December 31 , 2011
<br /> Task 2 : January and July (within 60 days of receipt of laboratory analysis )
<br /> Task 3 : Statement of Compliance March 1 , 2011
<br /> Annual Operating Report April 1 , 2011
<br /> Semi- Annual Operating Report March 1 , 2011 and September 1 , 2011
<br /> Annual Emissions Fee Between January 15, 2011 and March 1 , 2011
<br /> Task 4 : January 1 , 2011 through December 31 , 2011
<br /> Task 5 : January 2011 , April 2011 , July 2011 , and October 2011