ARTICLE 11 - SUBSTITUTE AND " OR- EQUAL" ITEMS <br /> 11 . 01 The Contract, if awarded , will be on the basis of materials and equipment specified or <br /> described in the Bidding Documents without consideration of possible substitute or "or-equal' <br /> items . Whenever it is specified or described in the Bidding Documents that a substitute or "or- <br /> equal" item of material or equipment may be furnished or used by CONTRACTOR if acceptable to <br /> ENGINEER , application for such acceptance will not be considered by ENGINEER until after the <br /> Effective Date of the Agreement. The procedure for submission of any such application by <br /> CONTRACTOR and consideration by ENGINEER is set forth in the General Conditions and may <br /> be supplemented in the General Requirements. <br /> ARTICLE 12 - SUBCONTRACTORS , SUPPLIERS , AND OTHERS <br /> 12 . 01 If the Supplementary Conditions require the identity of certain Subcontractors, Suppliers, <br /> individuals , or entities to be submitted to OWNER in advance of a specified date prior to <br /> the <br /> Effective Date of the Agreement, the apparent Successful Bidder, and any other Bidder so <br /> requested , shall within five days after Bid opening ,_ submit to OWNER a fist of aH such <br /> Subcontractors, Suppliers , individuals, or entities proposed for those portions of the Work for <br /> which such identification is required . Such list shall be accompanied by an experience statement <br /> with pertinent information regarding similar projects and other evidence of qualification for each <br /> such Subcontractor, Supplier, individual , or entity if requested by OWNER. If OWNER or <br /> ENGINEER , after due investigation , has reasonable objection to any proposed Subcontractor, <br /> Supplier, individual , or entity, OWNER may, before the Notice of Award is given , request apparent <br /> Successful Bidder to submit a substitute , without an increase in the Bid . <br /> 12 . 02 If apparent Successful Bidder declines to make any such substitution , OWNER may <br /> award the Contract to the next lowest Bidder that proposes to use acceptable Subcontractors, <br /> Suppliers , individuals , or entities . Declining to make requested substitutions will not constitute <br /> grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor, Supplier, individual , or <br /> entity so listed and against which OWNER or ENGINEER makes no written objection prior to the <br /> giving of the Notice of Award will be deemed acceptable to OWNER and ENGINEER subject to <br /> revocation of such acceptance after the Effective Date of the Agreement as provided in paragraph <br /> 6. 06 of the General Conditions . <br /> 12 . 03 CONTRACTOR shall not be required to employ any Subcontractor, Supplier, individual , or <br /> entity against whom CONTRACTOR has reasonable objection . <br /> ARTICLE 13 - PREPARATION OF BID <br /> 13 . 01 The Bid form is included with the Bidding Documents. Additional copies may be obtained <br /> from the Issuing Office . <br /> 13 . 02 All blanks on the Bid form shall be completed by printing in ink or by typewriter and the <br /> Bid signed . A Bid price shall be indicated for each section , Bid item , alternative , adjustment unit <br /> price item , and unit price item listed therein , or the words " No Bid , " " No Change , " or " Not <br /> Applicable" entered . <br /> 13 . 03 A Bid by a corporation shall be executed in the corporate name by the president or a vice- <br /> president or other corporate officer accompanied by evidence of authority to sign . The corporate <br /> 00200 = Instructions to Bidders REV 04=07.doc <br /> 00200 - 6 <br /> FAPubiic Works%ENGINEERING DIVISION PROJECTS10545=66Th Ave SR60 to 57th St (Arcadls)Wdmim\Bid Documents=200 - Instructions to Bidders REV 04-07.doc Rev. <br /> 05/01 <br /> I <br />