Laserfiche WebLink
C <br /> the delays, expense, and difficulties involved in proving in a legal proceeding the actual <br /> loss <br /> suffered by OWNER if the Work is not completed on time . Accordingly, instead of requiring any <br /> such proof, OWNER and CONTRACTOR agree that as liquidated damages for delay ( but not as a <br /> penalty) , CONTRACTOR shall pay OWNER $ 1 , 148 . 00 for each calendar day that expires after the <br /> time specified in paragraph 3 .02 for completion and readiness for final payment until the Work is <br /> completed and ready for final payment . <br /> ARTICLE 4 - CONTRACT PRICE <br /> 4 .01 OWNER shall pay CONTRACTOR for completion of the Work an amount in current funds equal to <br /> the sum of the amounts determined pursuant to paragraph 4 . 01 .A and summarized in paragraph <br /> 4 .01 . 13, below : <br /> A. For all Work, at the prices stated in CONTRACTOR' s Bid , attached hereto as an exhibit . <br /> Be THE CONTRACT SUM subject to additions and deductions provided in the Contract Documents : <br /> Numerical Amount : $ 1 , 168 ,000 . 00 <br /> Written Amount : One million one hundred sixty-eight thousand dollars and zero cents <br /> ARTICLE 5 - PAYMENT PROCEDURES <br /> 5 . 01 Progress Payments, <br /> A . The OWNER shall make progress payments to the CONTRACTOR on the basis of the <br /> approved partial payment request as recommended by ENGINEER in accordance with the <br /> provisions of the Local Government Prompt Payment Act, Florida Statutes section 218 . 70 <br /> et . seq . The OWNER shall retain ten percent ( 10% ) of the payment amounts due to the <br /> CONTRACTOR until fifty percent ( 50% ) completion of the work . After fifty percent ( 50% ) <br /> completion of the work is attained as certified to OWNER by ENGINEER in writing, OWNER <br /> shall retain five percent ( 5 % ) of the payment amount due to CONTRACTOR until final <br /> completion and acceptance of all work to be performed by CONTRACTOR under the <br /> Contract Documents . Pursuant to Florida Statutes section 218 . 735 ( 8 ) ( b ) , fifty percent <br /> ( 50% ) completion means the point at which the County as OWNER has expended fifty <br /> percent ( 50% ) of the total cost of the construction services work purchased under the Bid <br /> and Specification Documents, together with all costs associated with existing change <br /> orders and other additions or modifications to the construction services work provided <br /> under the Contract Documents . <br /> 5 . 02 Pay Requests. <br /> A . Each request for a progress payment shall contain the CONTRACTOR' S certification . All <br /> progress payments will be on the basis of progress of the work measured by the <br /> schedule of values established , or in the case of unit price work based on the number of <br /> units completed . After fifty percent ( 50% ) completion , and pursuant to Florida Statutes <br /> Page 2 of 7 <br />