My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
2012-021B
CBCC
>
Official Documents
>
2010's
>
2012
>
2012-021B
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
12/15/2015 1:23:01 PM
Creation date
10/1/2015 4:09:52 AM
Metadata
Fields
Template:
Official Documents
Official Document Type
Contract
Approved Date
02/14/2012
Control Number
2012-021B
Agenda Item Number
8.E.
Entity Name
Mancil Tractor Services
Subject
Contract Documents and Specifications Overflow and Vehicular Staging
Fairgrounds Events
Area
Indian River Fairgrounds Phase 2
Project Number
1047-2
Bid Number
2012028
Archived Roll/Disk#
112-R-0001
Supplemental fields
SmeadsoftID
10979
Jump to thumbnail
< previous set
next set >
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
204
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
SECTION 01310 <br /> CONSTRUCTION SCHEDULES <br /> 1 . 1 GENERAL REQUIREMENTS <br /> A . No partial payments shall be approved by the ENGINEER until there is an <br /> approved construction progress schedule on hand . <br /> B . Designate an authorized representative who shall be responsible for <br /> development and maintenance of the schedule and of all progress and <br /> payment reports . This representative shall have direct project control and <br /> complete authority to act on behalf of the CONTRACTOR in fulfilling the <br /> commitments of the CONTRACTOR ' s schedules . <br /> 1 . 2 REVISIONS TO THE CONSTRUCTION SCHEDULES <br /> When the ENGINEER requires the CONTRACTOR to submit revised ( updated ) <br /> progress schedules on a monthly basis the CONTRACTOR shall : <br /> A . Indicate the progress of each activity to the date of submission . <br /> B . Show changes occurring since the previous submission listing : <br /> 1 . Major changes in scope . <br /> 2 . Activities modified since the previous submission . <br /> 3 . Revised projections of progress and completion . <br /> 4 . Other identifiable changes . <br /> Co Provide a narrative report as needed to define : <br /> 1 . Problem areas , anticipated delays , and the impact on the schedule . <br /> 2 . Corrective action recommended and its effect . <br /> 3 . The effect of changes on schedules of other prime contractors . <br /> 1 . 3 SUBMISSION OF THE CONSTRUCTION SCHEDULES <br /> On or before the tenth day after the effective date of the Agreement , submit the <br /> initial schedules to the ENGINEER . The ENGINEER will review the schedules <br /> and return a review copy to the CONTRACTOR within 21 days after receipt . If <br /> required by the ENGINEER , resubmit revised schedules on or before the <br /> seventh day after receipt of the review copy . If required by the ENGINEER , <br /> submit revised monthly progress schedules with that month ' s application for <br /> 01310- 1 01310 Construction Schedule <br /> F : \PublicWorks\ENGINEERING DIVISION PROJECTS \1047-2 IRC Fairgrounds Overflow & Vehicular Staging Phase 2\Admim \bid <br /> documents\01310 - Construction Schedule . doc <br />