13 . 05 OWNER May Stop the Work <br /> SC- 13 . 05 . A . Delete paragraph GC- 13. 05. A in its entirety and insert the following paragraph in its <br /> place: <br /> A . If the Work is defective , or CONTRACTOR fails to supply sufficient skilled <br /> workers or suitable materials or equipment , or fails to comply with permit <br /> requirements , or fails to comply with the technical specifications , or fails to <br /> perform the Work in such a way that the completed Work will conform to the <br /> Contract Documents , OWNER may order CONTRACTOR to stop the Work , or any <br /> portion thereof, until the cause for such order has been eliminated ; however, this <br /> right of OWNER to stop the Work shall not give rise to any duty on the part of <br /> OWNER to exercise this right for the benefit of CONTRACTOR , any <br /> Subcontractor, any Supplier, any other individual or entity , or any surety for, or <br /> employee or agent of any of them . <br /> 14 . 02 Progress Payments <br /> SC- 14 . 02 . B . 5 . Delete paragraph GC- 14. 02. B. 5. d in its entirety and insert the following paragraph <br /> in its place: <br /> d . ENGINEER has actual knowledge of the occurrence of any of the events <br /> enumerated in paragraph 15 . 02 . A; or <br /> SC- 14 . 02 . 13 . 5 . Add the following sentences at the end of paragraph GC- 14. 02. 8. 5: <br /> e . OWNER has been required to pay ENGINEER additional compensation because <br /> of CONTRACTOR delays or rejection of defective Work ; or <br /> f. OWNER has been required to pay an independent testing laboratory for <br /> subsequent inspections , tests , or approvals taken after initial failing <br /> inspections , tests , or approvals . <br /> SC- 14 . 02 . C . 1 . Delete paragraph GC- 14. 02. C. 1 in its entirety and insert the following paragraph in <br /> its place : <br /> C . Payment Becomes Due <br /> 1 . Payment shall be made by OWNER to CONTRACTOR according to the Local <br /> Government Prompt Payment Act , F . S . 218 . 70 et. seq . <br /> SC- 14 . 04A . After the third sentence in paragraph GC- 14. 04A of the General Conditions, <br /> delete the remainder of paragraph 14. 04A in its entirety and replace with the following: <br /> " If Engineer considers the Work substantially complete , Engineer will prepare <br /> and deliver to Owner a tentative certificate of Substantial Completion that shall fix <br /> the date of Substantial Completion . In accordance with the provisions of Florida <br /> Statutes section 208 . 735 (7 ) (x ) (2005 ) , upon receipt of the tentative certificate of <br /> Substantial Completion from Engineer, the Owner, the Engineer, and the <br /> Contractor shall conduct a walk-through inspection of the Project to document a <br /> list of any items required to render the Work on the Project complete , <br /> satisfactory , and acceptable under this Agreement ( herein the " Statutory List" ) . <br /> The Statutory List shall be reduced to writing and circulated among the Owner, <br /> the Engineer, and the Contractor by the Owner or the Engineer within 30 <br /> calendar days after substantial completion . The Owner and Contractor <br /> 00800-7 <br /> 00800 - Supplementary Conditions 06-09 rev.doc <br /> 00800 FAPublic Works\ENGINEERING DIVISION PROJECTS\0744-8th St-USI to 6th Ave\Admim\bid documents\0744 CONTRACT DOCUMENTS\00800 - Supplementary <br /> Conditions 06-09 rev.doc <br />