Be This project includes renovation of 66 rooms . The rooms will be renovated in groups of <br /> five (5) at a time . Each group must be completed within nineteen ( 19) calendar days . <br /> ( NOTE : One group of six (6) will be combined together that require less work. Time <br /> allotted for the six (6) rooms will be completed within nineteen ( 19) calendar days . ) The <br /> intent is to have the first group of five (5) rooms begin on Monday and be completed in <br /> nineteen ( 19) calendar days (end Friday) . Then the second group of five (5) rooms will <br /> begin on Monday and be completed in the next nineteen ( 19) calendar days (end Friday) , <br /> etc . However, due to holidays and special events , the schedule may be modified , but in no <br /> case will the contractor be required to de- mobilize for longer than nineteen ( 19) calendar <br /> days at one time and not more than two occurrences . Additionally no rooms can be out of <br /> service from December 20 , 2013 to December 30 , 2013 and from February 20 , 2014 to <br /> April 15 , 2014 . <br /> The tentative schedule is as follows : <br /> 1St Group 11 /04/2013to 11 /22/2013 <br /> 2nd Group 11 /25/2013to 12/ 17/2013 (includes 4 days not counted for <br /> Thanksgiving day and weekend) <br /> 3`d Group 1 /06/2014 to 1 /24/2014 <br /> 4th Group 1 /27/2014 to 2/ 14/2014 <br /> 5th Group 4/21 /2014 to 5/09/2014 <br /> 6th Group 5/ 12/2014 to 5/31 /2014 (Saturday , due to Memorial Day) <br /> 7th Group 6/02/2014 to 6/20/2014 <br /> 8th Group 6/23/2014 to 7/ 12/2014 (Saturday , due to Independence Day) <br /> 9th Group 7/ 14/2014 to 8/01 /2014 <br /> 10th Group 8/04/2014 to 8/22/2014 <br /> 11th Group 8/25/2014 to 9/ 13/2014 (Saturday , due to Labor Day) <br /> 12th Group 9/ 15/2014 to 10/3/2014 <br /> 13th Group 10/06/2014to 10/24/2014 <br /> Please note , the schedule is tentative and may be adjusted as rooms are available for <br /> work ( not rented) . There are times during the slow season ( normally April 16 — August 1 ) <br /> that more than 5 rooms can be renovated at the same time . But, other than the blackout <br /> dates listed above , there will not be more than 2 additional occurrences , as shown above , <br /> where the contractor will be required to de-mobilize , unless the contractor is agreeable to <br /> additional changes . <br /> A Notice to Proceed will be issued for each group . On Day Sixteen ( 16) of the nineteen <br /> ( 19) calendar days , a walk-through will be conducted and a Certificate of Substantial <br /> Completion , along with a list of items to be completed or corrected will be issued . Said <br /> work to be completed within three (3) calendar days . <br /> 4 . 03 Liquidated Damages <br /> A . CONTRACTOR and OWNER recognize that time is of the essence of this Agreement <br /> and that OWNER will suffer financial loss if the Work is not completed within the times <br /> specified in paragraph 4 . 02 above , plus any extensions thereof allowed in accordance <br /> with Article 12 of the General Conditions . Liquidated damages will commence for this <br /> portion of work . The parties also recognize the delays , expense , and difficulties involved <br /> in proving in a legal proceeding the actual loss suffered by OWNER if the Work is not <br /> completed on time . Accordingly , instead of requiring any such proof, OWNER and <br /> CONTRACTOR agree that as liquidated damages for delay ( but not as a penalty) , <br /> 00520 - Agreement (Public Works) REVISED 09-27-2013 per Addendum <br /> 00520 - 3 <br /> \\Fileserver2\Public\Purchasing\Bids\2013-2014 FY (2014000)\2014003 VBSV Dorm Renovations\00520 - Agreement (Public Works) REVISED 09-27-2013 per Addendum.doc <br />