F . The divisions and sections of the Specifica- dispute resolution costs ) arising out of or
<br /> relating to
<br /> tions and the identifications of any Drawings shall not any infringement of patent rights or copyrights incident
<br /> control CONTRACTOR in dividing the Work among to the use in the performance of the Work or resulting
<br /> Subcontractors or Suppliers or delineating the Work to from the incorporation in the Work of any invention
<br />,
<br /> be performed by any specific trade . design , process , product, or device not specified in the
<br /> Contract Documents .
<br /> G . All Work performed for CONTRACTOR by a
<br /> Subcontractor or Supplier will be pursuant to an 6 . 08 Permits
<br /> appropriate agreement between CONTRACTOR and
<br /> the Subcontractor or Supplier which specifically binds A. Unless otherwise provided in the Supple-
<br /> the Subcontractor or Supplier to the applicable terms mentary Conditions , CONTRACTOR shall obtain and
<br /> and conditions of the Contract Documents for the pay for all construction permits and licenses . OWNER
<br /> benefit of OWNER and ENGINEER . Whenever any shall assist CONTRACTOR , when necessary, in
<br /> such agreement is with a Subcontractor or Supplier obtaining such permits and licenses . CONTRACTOR
<br /> who is listed as an additional insured on the property shall pay all governmental charges and inspection
<br /> insurance provided in paragraph 5 . 06 , the agreement fees necessary for the prosecution of the Work which
<br /> between the CONTRACTOR and the Subcontractor are applicable at the time of opening of Bids,
<br />or, if
<br /> or Supplier will contain provisions whereby the there are no Bids , on the Effective Date of the
<br /> Subcontractor or Supplier waives all rights against Agreement. CONTRACTOR shall pay all charges of
<br /> OWNER , CONTRACTOR , ENGINEER , ENGINEER ' s utility owners for connections to the Work , and
<br /> Consultants, and all other individuals or entities OWNER shall pay all charges of such utility owners
<br /> identified in the Supplementary Conditions to be listed for capital costs related thereto , such as plant
<br /> as insureds or additional insureds (and the officers , investment fees.
<br /> directors , partners , employees , agents , and other
<br /> consultants and subcontractors of each and any of 6 . 09 Laws and Regulations
<br /> them ) for all losses and damages caused by, arising
<br /> out of, relating to , or resulting from any of the perils or A. CONTRACTOR shall give all notices and
<br /> causes of loss covered by such policies and any other comply with all Laws and Regulations applicable to the
<br /> property insurance applicable to the Work . If the performance of the Work . Except where otherwise
<br /> insurers on any such policies require separate waiver expressly required by applicable Laws and
<br /> forms to be signed by any Subcontractor or Supplier, Regulations , neither OWNER nor ENGINEER shall be
<br /> CONTRACTOR will obtain the same , responsible for monitoring CONTRACTOR' s complk
<br /> ance with any Laws or Regulations.
<br /> 6 . 07 Patent Fees and Royalties
<br /> B . If CONTRACTOR performs any Work know-
<br /> A. CONTRACTOR shall pay all license fees and ing or having reason to know that it is contrary to Laws
<br /> royalties and assume all costs incident to the use in or Regulations , CONTRACTOR shall bear all claims
<br />,
<br /> the performance of the Work or the incorporation in costs , losses , and damages ( including but not
<br /> limited
<br /> the Work of any invention , design , process , product, to all fees and charges of engineers , architects ,
<br /> or device which is the subject of patent rights or attorneys , and other professionals and all court
<br /> or
<br /> copyrights held by others . If a particular invention , arbitration or other dispute resolution costs) arising
<br /> out
<br /> design , process , product, or device is specified in the of or relating to such Work ; however, it
<br /> shall not be
<br /> Contract Documents for use in the performance of the CONTRACTOR ' s primary responsibility to make
<br /> Work and if to the actual knowledge of OWNER or certain that the Specifications and Drawings
<br /> are in
<br /> ENGINEER its use is subject to patent rights or accordance with Laws and Regulations , but this shall
<br /> copyrights calling for the payment of any license fee or not relieve CONTRACTOR of CONTRACTOR ' s
<br /> royalty to others , the existence of such rights shall be obligations under paragraph 3 . 03 .
<br /> disclosed by OWNER in the Contract Documents . To
<br /> the fullest extent permitted by Laws and Regulations , C . Changes in Laws or Regulations not known at
<br /> CONTRACTOR shall indemnify and hold harmless the time of opening of Bids (or, on the Effective Date
<br /> OWNER , ENGINEER , ENGINEER ' s Consultants , and of the Agreement if there were no Bids) having an
<br /> the officers , directors , partners , employees or agents , effect on the cost or time of performance of the Work
<br /> and other consultants of each and any of them from may be the subject of an adjustment in Contract Price
<br /> and against all claims , costs , losses , and damages or Contract Times . If OWNER and CONTRACTOR
<br /> ( including but not limited to all fees and charges of are unable to agree on entitlement to or on the
<br /> engineers, architects , attorneys , and other amount or extent, if any , of any such adjustment, a
<br /> professionals and all court or arbitration or other
<br /> 00700 - General Conditions REV 5-10-13. doc
<br /> 00700 - 22
<br /> F:\Public Works\ENGINEERING DIVISION PROJECTS\1 341 -Historic Dodgertown (fka VB Sports Village) Room Renovations)VAdmin\bid documents\Master Contract Docs\Master
<br /> Contract
<br /> Documents\00700 - General Conditions REV 5- 10-13. doc
<br />
|