EXHIBIT 43 ' <br /> TIME SCHEDULE <br /> WORK ORDER NO. 1 <br /> Time of Performance <br /> The estimated time frame for completion ofservices from the approval val of this Work <br /> Order is as follows : <br /> Phase 1 — Preliminar En ineerin <br /> Route Survey, Engineering Evaluation & <br /> Hydraulic Analysis , preliminary plans, cost estimate 2 Months <br /> Phase 2 — Final design and Permitting : <br /> - Survey of WWTp , Geotechnical data, Engineering 3 <br /> Design &, preparation of Construction Plans, Months <br /> Specifications and Bid Documents <br /> Submittal of Permit Applications and Receipt of permits 2 Months <br /> Phase 3 — Procurement and Construction : <br /> Bidding, Contract Award <br /> 2 Months <br /> Construction administration and periodic <br /> construction field inspections 6 Months <br /> Remainder of Page Intentionally Left Blank <br /> P . 1 of 1 <br />