EXHIBIT 63 ' <br /> TIME SCHEDULE <br /> WORK ORDER NO. 2 <br /> Time of Performance <br /> The estimated time frame for completion of services from the approval of this Work Authorization is a follows : <br /> I . Preliminary Plan review and evaluation I month <br /> 2 . Engineering Design & Preparation of 2 Months <br /> Construction Plans, specifications and Bid Documents <br /> 2 . Submittal of Permit Applications and Receipt ol' permits I Months <br /> And Bidding/Contract Award ( Done Concurrently ) <br /> 3 . Construction 3 %s Months ( 15 weeks) <br /> Remainder of Page Intentionally Left Blank <br />