Laserfiche WebLink
5 . Such request is for information only , and is not an instruction to execute the <br /> changes , nor to stop work in progress . <br /> B . Contractor may initiate changes by submitting a written notice to Owner, containing : <br /> I . Description of the proposed changes <br /> 2 . Statement of the reason for making the changes . <br /> 3 . Statement of the effect on the Contract Sum and the Contract Time . <br /> 4 . Statement of the effect on the work of separate contractors . <br /> 5 . Documentation supporting any changes in Contract Sum or Contract Time, as <br /> appropriate . <br /> 1 . 05 CONSTRUCTION CHANGE AUTHORIZATION <br /> A . In lieu of Proposal Request, Owner may issue a " Work Directive Change " for Contractor <br /> to proceed with a change for subsequent inclusion in a Change Order. <br /> B . Authorization will describe changes in the work, both additions and deletions , with <br /> attachments of revised Contract Documents to define details of the change . <br /> C . Owner will sign and date the Work Directive Change as authorization for the Contractor <br /> to proceed with the Changes . <br /> 1 . 06 DOCUMENTATION OF PROPOSALS AND CLAIMS <br /> A . Support each quotation for a lump sum proposal , and for each unit price which has not <br /> previously been established , with sufficient substantiating data to allow Owner to <br /> evaluate the quotation . <br /> B . On request, provide additional data to support tirne and cost computation including the <br /> following : <br /> I . Labor required . <br /> 2 . Equipment required . <br /> 3 . Products required : <br /> a . Recommended source of purchase and unit cost. <br /> b . Quantities required . <br /> 4 . Taxes , insurance bonds . <br /> 5 . Credit for work deleted from Contract, similarly documented . <br /> 6 . Overhead and profit. <br /> 7 . Justification for any change in Contract Time . <br /> C . Support each claim for additional costs , and for work done on a time- and - material / force <br /> account basis , with documentation as required fora hung sum proposal , plus the <br /> following additional information : <br /> 1 . Name of the Owner' s authorization agent who ordered the work, and date of the <br /> order. <br /> 2 . Dates and time work performed , and by whom . <br /> 3 . Time record , sununary of hours worked , and hourly rates paid . <br /> 4 . Receipts and invoices for : <br /> a . Equipment used , listing dates and times of use . <br /> b . Products used , listing quantities . <br /> C . Subcontracts . <br /> 01035 - 2 <br />