444 <br /> • ARTICLE 12 - CHANGE OF CONTRACT PRICE ; CHANGE OF <br /> CONTRACT TIMES <br /> SC 12 . 01 A . Delete paragraph 12 , 01A of the General Conditions in its entirety and replace with the following : <br /> The Contract Price may only be changed by a Change Order or by a Written Amendment. Any Claim for an <br /> adjustment in the Contract Price shall be based on written notice in accordance with the provisions of paragraph <br /> 10 . 05 . <br /> SC 12 . 01132 . Delete paragraph 12 . 01 B2 of the General Conditions in its entirety and replace with the following : <br /> 2 . where the Work involved is not covered by unit prices contained in the Contract Documents , by a mutually <br /> agreed lump sum . <br /> SC 12 . 01133 . Delete paragraph 12 . 01133 of the General Conditions in its entirety . <br /> SC 12 . 01C . Delete paragraph 12 . 01 C of the General Conditions in its entirety . <br /> 12 . 03A and B . Delete paragraphs 12 . 03 . A and 12 . 0313 of the General Conditions in their entirety and replace <br /> with the following : <br /> A . Where Contractor is delayed or prevented from completing any part of the Work within the Contract <br /> Times due to delay beyond the control of Contractor, the Contract Times (or Milestones) will be extended in an <br /> amount equal to the time lost due to such delay ifs a Claim is made therefore as provided in paragraph 12 . 02 . A <br /> and (2) Contractor provides evidence that the delay impacted the critical path of the Project. Delays beyond the <br /> control of Contractor shall include, but not be limited to , acts or neglect by Owner, acts or neglect of <br /> utility <br /> owners or other contractors performing other work as contemplated by Article 7 , fires , floods, abnormal weather <br /> conditions or acts of God . The Contractor must request the extension of time in writing and must provide the <br /> following information within the time periods stated hereafter. Failure to submit such information and <br /> in <br /> compliance with the time requirements hereinafter stated, shall constitute a waiver by the Contractor and a denial <br /> of the claim for extension of time : <br /> I . Nature of the delay or change in the Work ; <br /> 2 . Dates of commencement and cessation of the delay or change in the Work ; <br /> 3 . Activities on the current progress schedule affected by the delay or change in the Work; <br /> 4 . Identification and demonstration that the delay or change in Work affects the critical path ; <br /> 5 . Identification of the source of delay or change in the Work; <br /> 6 . Anticipated extent of the delay or change in the Work ; and <br /> 7 . Recommended action to minimize the delay . <br /> B . Contractor hereby affirms that the extension of time granted herein is the Contractor' s sole and exclusive <br /> remedy . Apart from extension of time, no payment or claim for damages shall be made to the Contractor as <br /> compensation for damages for any delays or hindrances from any cause whatsoever in the progress of the Work <br /> whether such delay is avoidable or unavoidable . <br /> SC 12 . 03C . Delete paragraph 12 . 03 . 0 of the General Conditions in its entirety . <br /> SC 12 . 03D . Delete paragraph 12 . 03D of the General Conditions in its entirety and replace with the following : <br /> In no event shall Owner, Engineer, or the Related Entities of either of them be liable to <br /> Contractor, any <br /> Subcontractor, any Supplier, any other person or organization , or any surety for or employee or agent of any of <br /> them , for any claim , cost, loss , or damages of any nature whatsoever arising out of or resulting from delays . <br /> 00800- 12 <br />