IT ART <br /> eL <br /> • SECTION 01035 <br /> CHANGE ORDER PROCEDURES <br /> PART 1 - GENERAL <br /> 1 . 01 REQUIREMENTS INCLUDE <br /> A . Promptly implement Change Order Procedures <br /> I . Provide full written data required to evaluate changes . <br /> - 2 . Maintain detailed records of work done on a time- and -material/force account <br /> basis . <br /> 3 . Provide full documentation to Engineer on request. <br /> B . Designate in writing the member of Contractor ' s organization : <br /> 1 . Who is authorized to accept changes in the Work, <br /> 2 . Who is responsible for informing others in the Contractor ' s employ of the <br /> authorization of changes in the Work. <br /> C . Owner will designate in writing the person who is authorized to execute Change Orders . <br /> 1 . 02 RELATED REQUIREMENTS <br /> A . The amount of established unit prices . <br /> B . Conditions of the Contract : <br /> 1 . Methods of determining cost or credit to Owner resulting from changes in Work <br /> made on a time- and -materials basis . <br /> 2 . Contractor ' s claims for additional costs . <br /> C . Applications for Payment are included in Section 01052 , <br /> 1 <br /> D . Construction Schedules is included in Section 0131 1 . ; <br /> E . Schedule of Values is included in Section 01370 . <br /> 1 . 03 DEFINITIONS <br /> A . Change Order : See General Conditions <br /> 1 . 04 PRELIMINARY PROCEDURES <br /> A . Owner or Engineer may initiate changes by submitting a proposal Request to Contractor . <br /> Request will include the following : <br /> 1 . Detailed description of the Change , Products , and location of the change in the <br /> Project , <br /> 2 . Supplementary or revised Drawings and Specifications . <br /> 3 . The projected time span for making the change, and a specific statement as to <br /> whether overtime work is , or is not, authorized . <br /> 4 . A specific period of time during which the requested price will be considered <br /> valid . <br /> 01035 - 1 <br />