SECTION 01170 <br /> SPECIAL PROVISIONS <br /> PART 1 — GENERAL <br /> 1901 INSTALLATION OF EQUIPMENT <br /> A . Special care shall be taken to ensure proper alignment of all equipment with particular <br /> reference to the pumps and electric drives . The units shall be carefully aligned on their <br /> foundations by qualified millwrights after their sole plates have been shimmed to true <br /> alignment at the anchor bolts . The anchor bolts shall be set in place and the nuts tightened <br /> against the shims . After the foundation alignments have been completed, the bedplates or <br /> wing feet of the equipment shall be securely bolted in place . The alignment of equipment <br /> shall be further checked after securing to the foundations , and after conformation of all <br /> alignments , the sole plates shall be finally grouted in place . The Contractor shall be <br /> responsible for the exact alignment of equipment with associated piping and under no <br /> circumstances , will "pipe springing " be allowed . <br /> Be All wedges , shims, filling pieces , keys , packing , grout, or other materials necessary to <br /> properly align , level and secure apparatus in place shall be furnished by the Contractor. <br /> All parts intended to be plumb or level must be proven exactly so . Perform all grinding <br /> necessary to bring parts to proper bearing after erection . <br /> 1 . 02 SLEEVES AND OPENINGS <br /> A . Provide all openings, channels, chases , etc , in new construction and furnish and install <br /> anchor bolts and other items to be embedded in concrete , as required to complete the <br /> work under this Contract . Perform all cutting , coring and rough and finish patching <br /> required in existing construction for the work of all trades . <br /> Be Subcontractors shall furnish all sleeves , inserts , hangers, anchor bolts , etc , required for <br /> the execution of their work . It shall be their responsibility before the work of the <br /> Contractor is begun to furnish him with the above items and with templates , drawings or <br /> written information covering chases , openings , etc, which they require and to follow up <br /> the work of the Contractor as it progresses, making sure that their drawings and written <br /> instructions are carried out . Failing to do this , they shall be responsible for the cost of any <br /> corrective measures which may be required to provide necessary openings, etc . If the <br /> Contractor fails to carry out the directions given him , covering details and locations of <br /> openings , etc , he shall be responsible for any cutting and refinishing required to make the <br /> necessary corrections . In no case shall beams , lintels, or other structural members be cut <br /> without the approval of the Engineer . <br /> 1 . 03 RELOCATION <br /> A . The Contractor shall be responsible for the relocation of structures , including but not <br /> limited to light poles , signs, sign poles , fences , piping , conduits and drains that interfere <br /> with the positioning of the work as set out on the Drawings . The cost of all such <br /> 01170 - 1 <br />