directly or indirectly employed by any of them or 3 . Any part of Contractor ' s capital expenses,
<br /> for whose acts any of them may be liable, and including interest on Contractor ' s capital employed
<br /> royalty payments and fees for permits and for the Work and charges against Contractor for
<br /> licenses . delinquent payments .
<br /> f. Losses and damages (and related expenses) 4 . Costs due to the negligence of Contractor,
<br /> any
<br /> caused by damage to the Work, not compensated Subcontractor, or anyone directly or indirectly
<br /> by insurance or otherwise, sustained by employed by any of them or for whose acts any of
<br /> Contractor in connection with the performance them may be liable, including but not limited to, the
<br /> of the Work ( except losses and damages within correction of defective Work , disposal of materials or
<br /> the deductible amounts of property insurance equipment wrongly supplied, and making good any
<br /> established in accordance with Paragraph damage to property .
<br /> 5 . 06 . D) , provided such losses and damages have
<br /> resulted from causes other than the negligence of 5 . Other overhead or general expense costs of any
<br /> Contractor, any Subcontractor, or anyone kind and the costs of any item not specifically and
<br />,
<br /> directly or indirectly employed by any of them or expressly included in Paragraphs 1 LO LA and
<br /> for whose acts any of them may be liable . Such 1 1 . 01 . 13 .
<br /> losses shall include settlements made with the
<br /> written consent and approval of Owner. No such C . Contractor 's Fee: When all the Work is performed on
<br /> losses, damages , and expenses shall be included the basis of cost-plus, Contractor ' s fee shall be
<br /> in the Cost of the Work for the purpose of determined as set forth in the Agreement.
<br /> When the value
<br /> determining Contractor ' s fee . of any Work covered by a Change Order or when a Claim
<br /> for an adjustment in Contract Price is determined on the
<br /> g. The cost of utilities, fuel , and sanitary basis of Cost of the Work, Contractor ' s fee shall be
<br /> facilities at the Site . determined as set forth in Paragraph 12 . 01 . C .
<br /> h . Minor expenses such as telegrams, long D . Documentation: Whenever the Cost of the Work for
<br /> distance telephone calls, telephone service at the any purpose is to be determined pursuant to Paragraphs
<br /> Site, expresses, and similar petty cash items in 1 LOLA and 11 . 01 . 13 . Contractor will establish
<br /> and
<br /> connection with the Work. maintain records thereof in accordance with generally
<br /> accepted accounting practices and submit in a form
<br /> i . The costs of premiums for all bonds and acceptable to Engineer an itemized cost breakdown
<br /> insurance Contractor is required by the Contract together with supporting data.
<br /> Documents to purchase and maintain .
<br /> 11 . 02 Allowances
<br /> B . Costs Excluded: The term Cost of the Work shall not
<br /> include any of the following items : A . It is understood that Contractor has included in the
<br /> Contract Price all allowances so named in the Contract
<br /> 1 . Payroll costs and other compensation of Documents and shall cause the Work so covered to be
<br /> Contractor ' s officers, executives, principals (of performed for such sums and by such persons or entities
<br /> partnerships and sole proprietorships) , general as may be acceptable to Owner and Engineer.
<br /> managers, safety managers , engineers , architects,
<br /> estimators , attorneys , auditors, accountants, B . Cash Allowances
<br /> purchasing and contracting agents , expediters,
<br /> timekeepers, clerks, and other personnel employed by 1 . Contractor agrees that :
<br /> Contractor, whether at the Site or in Contractor ' s
<br /> principal or branch office for general administration a . the cash allowances include the cost to
<br /> of the Work and not specifically included in the Contractor ( less any applicable trade discounts)
<br /> agreed upon schedule of job classifications referred of materials and equipment required by the
<br /> to in Paragraph 11 . 01 . A . I or specifically covered by allowances to be delivered at the Site,
<br /> and all
<br /> Paragraph 11 . O1 . A .4 , all of which are to be applicable taxes ; and
<br /> considered administrative costs covered by the
<br /> Contractor ' s fee . b . Contractor ' s costs for unloading and handling
<br /> on the Site, labor, installation , overhead , profit,
<br /> 2 . Expenses of Contractor ' s principal and branch and other expenses contemplated for the cash
<br /> offices other than Contractor ' s office at the Site , allowances have been included in the Contract
<br /> Price and not in the allowances , and no demand
<br /> for additional payment on account of any of the
<br /> foregoing will be valid .
<br /> C . Contingency Allowance
<br /> EJCDC C-700 Standard General Conditions of the Construction Contract.
<br /> Copyright © 2002 national Society of Professional Engineers for EJCDC. All rights reserved.