15 . 02 Owner May Terminate for Cause D . Notwithstanding Paragraphs 15 . 02 . 13 and 15 . 02 . 0, <br /> Contractor ' s services will not be terminated if Contractor <br /> A . The occurrence of any one or more of the following begins within seven days of receipt of notice of intent to <br /> events will justify termination for cause : terminate to correct its failure to perform and proceeds <br /> 1 . Contractor ' s persistent failure to erform the diligently to cure such failure within no more than 30 <br /> Work in accordance with the ContractDocuments <br /> days of receipt of said notice. <br /> ( including, but not limited to, failure to supply suffi - E. Where Contractor ' s services have been so terminated <br /> tient skilled workers or suitable materials or equip - by Owner, the termination will not affect any rights <br /> or <br /> ment or failure to adhere to the Progress Schedule remedies of Owner against Contractor then existing or <br /> established under Paragraph 2 . 07 as adjusted from which may thereafter accrue . Any retention or payment <br /> of <br /> time to time pursuant to Paragraph 6 . 04) ; moneys due Contractor by Owner will not release <br /> 2 . Contractor ' s disregard of Laws or Regulations of Contractor from liability . <br /> any public body having jurisdiction ; F . If and to the extent that Contractor has provided a <br /> 3 . Contractor ' s disregard of the authority of performance bond under the provisions of Paragraph <br /> Engineer; or y 5 , 01 . A , the termination procedures of that bond shall <br /> supersede the provisions of Paragraphs 15 . 02 . 13 , and <br /> 4 . Contractor ' s violation in any substantial way of 15 . 02 . C, <br /> any provisions of the Contract Documents , 15 . 03 Owner May Terminate For Convenience <br /> B . If one or more of the events identified in Paragraph A . Upon seven days written notice to Contractor and <br /> 15 . 02 . A occur, Owner may , after giving Contractorand <br /> ( Engineer, Owner may, without cause and without <br /> surety) seven days written notice of its intent to terminate <br /> prejudice to any other right or remedy of Owner, <br /> the services of Contractor: terminate the Contract . In such case, Contractor shall be <br /> 1 . exclude Contractor from the Site, and take Paid for (without duplication of any items) : <br /> possession of the Work and of all Contractor ' s tools , 1 . completed and acceptable Work executed in <br /> appliances, construction equipment, and machinery at accordance with the Contract Documents prior to the <br /> the Site, and use the same to the full extent they effective date of termination , including fair and <br /> could be used by Contractor (without liability to reasonable sums for overhead and profit <br /> on such <br /> Contractor for trespass or conversion), <br /> Work ; <br /> 2 . incorporate in the Work all materials and 2 . expenses sustained prior to the effective date of <br /> equipment stored at the Site or for which Owner has <br /> termination in performing services and furnishing <br /> paid Contractor but which are stored elsewhere, and labor, materials, or equipment as required by <br /> the <br /> 3 . complete the Work as Owner may deem Contract Documents in connection with uncompleted <br /> expedient. y Work, plus fair and reasonable sums for overhead <br /> and profit on such expenses ; <br /> C . If Owner proceeds as provided in Paragraph 15 . 02 . 13 , <br /> 3 • all claims, costs, losses, and damages ( including <br /> Contractor shall not be entitled to receive any further <br /> but not limited to all fees and charges of engineers , <br /> payment until the Work is completed . If the unpaid architects, attorneys , and other professionals and all <br /> balance of the Contract Price exceeds all claims, costs, <br /> court or arbitration or other dispute resolution costs) <br /> losses , and damages (including but not limited to all fees <br /> and charges of engineers, architects, attorneys, and other incurred in settlement of terminated contracts with <br /> Subcontractors, Suppliers, and others ; and <br /> professionals and all court or arbitration or other dispute <br /> resolution costs) sustained by Owner arising out of or 4 . reasonable expenses directly attributable to <br /> relating to completing the Work, such excess will be paid termination . <br /> to Contractor. If such claims , costs, losses, and damages <br /> exceed such unpaid balance, Contractor shall pay the B . Contractor shall not be paid on account of loss of <br /> difference to Owner. Such claims, costs , losses, and anticipated profits or revenue or other economic loss <br /> damages incurred by Owner will be reviewed by Engineer arising out of or resulting from such termination . <br /> as to their reasonableness and , when so approved by <br /> Engineer, incorporated in a Change Order. When 15 . 04 Contractor May Stop Work or Terminate <br /> exercising any rights or remedies under this Paragraph <br /> Owner shall not be required to obtain the lowest price for A . If, through no act or fault of Contractor, ( i <br />) the Work is <br /> the Work performed . suspended for more than 90 consecutive days by Owner <br /> or under an order of court or other public authority, or ( ii ) <br /> Engineer fails to act on any Application for Payment <br /> EJCDC C-700 Standard General Conditions of the Construction Contract. -- <br /> Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. <br /> 00700 - 40 <br /> y. <br />