G . All Work performed for CONTRACTOR by a 6 . 08 Permits
<br /> Subcontractor or Supplier will be pursuant to an
<br /> appropriate agreement between CONTRACTOR and A. Unless otherwise provided in the Supple-
<br /> the Subcontractor or Supplier which specifically binds mentary Conditions , CONTRACTOR shall obtain and
<br /> the Subcontractor or Supplier to the applicable terms pay for all construction permits and licenses . OWN .
<br /> and conditions of the Contract Documents for the ER shall assist CONTRACTOR , when necessary, in
<br /> benefit of OWNER and ENGINEER . Whenever any obtaining such permits and licenses . CONTRACTOR
<br /> such agreement is with a Subcontractor or Supplier shall pay all governmental charges and inspection
<br /> who is listed as an additional insured on the property fees necessary for the prosecution of the Work which
<br /> insurance provided in paragraph 5 . 06 , the agreement are applicable at the time of opening of Bids ,
<br /> or, if
<br /> between the CONTRACTOR and the Subcontractor there are no Bids , on the Effective Date of the
<br /> or Supplier will contain provisions whereby the Agreement. CONTRACTOR shall pay all charges of
<br /> Subcontractor or Supplier waives all rights against utility owners for connections to the Work , and
<br /> OWNER , CONTRACTOR , ENGINEER , OWNER shall pay all charges of such utility owners
<br /> ENGINEER ' s Consultants , and all other individuals or for capital costs related thereto, such as plant
<br /> entities identified in the Supplementary Conditions to investment fees,
<br /> be listed as insureds or additional insureds (and the
<br /> officers , directors , partners , employees , agents , and 6 . 09 Laws and Regulations
<br /> other consultants and subcontractors of each and any
<br /> of them ) for all losses and damages caused by, A. CONTRACTOR shall give all notices and
<br /> arising out of, relating to, or resulting from any of the comply with all Laws and Regulations applicable
<br /> to
<br /> perils or causes of loss covered by such policies and the performance of the Work. Except where
<br /> any other property insurance applicable to the Work, otherwise expressly required by applicable Laws and
<br /> If the insurers on any such policies require separate Regulations , neither OWNER nor ENGINEER shall
<br /> waiver forms to be signed by any Subcontractor or be responsible for monitoring CONTRACTOR 's
<br /> Supplier, CONTRACTOR will obtain the same. compliance with any Laws or Regulations .
<br /> 6 . 07 Patent Fees and Royalties B . If CONTRACTOR performs any Work know-
<br /> ing or having reason to know that it is contrary to
<br /> A. CONTRACTOR shall pay all license fees and Laws or Regulations , CONTRACTOR shall bear all
<br /> royalties and assume all costs incident to the use in claims , costs , losses , and damages ( including but
<br /> not
<br /> the performance of the Work or the incorporation in limited to all fees and charges of engineers ,
<br /> the Work of any invention , design , process , product, architects , attorneys , and other professionals and all
<br /> or device which is the subject of patent rights or court or arbitration or other dispute resolution
<br /> costs)
<br /> copyrights held by others . If a particular invention , arising out of or relating to such Work ;
<br /> however, it
<br /> design , process , product, or device is specified in the shall not be CONTRACTOR 's primary responsibility
<br /> Contract Documents for use in the performance of to make certain that the Specifications and Drawings
<br /> the Work and if to the actual knowledge of OWNER are in accordance with Laws and Regulations , but this
<br /> or ENGINEER its use is subject to patent rights or shall not relieve CONTRACTOR of CONTRACTOR ' s
<br /> copyrights calling for the payment of any license fee obligations under paragraph 3 . 03 .
<br /> or royalty to others , the existence of such rights shall
<br /> be disclosed by OWNER in the Contract Documents . C . Changes in Laws or Regulations not known
<br /> To the fullest extent permitted by Laws and Regula- at the time of opening of Bids (or, on the
<br /> Effective
<br /> tions , CONTRACTOR shall indemnity and hold Date of the Agreement if there were no Bids) having
<br /> harmless OWNER , ENGINEER , ENGINEER ' s an effect on the cost or time of performance of the
<br /> Consultants , and the officers , directors , partners , Work may be the subject of an adjustment in Contract
<br /> employees or agents , and other consultants of each Price or Contract Times , If OWNER and
<br /> and any of them from and against all claims , costs , CONTRACTOR are unable to agree on entitlement to
<br /> losses , and damages ( including but not limited to all or on the amount or extent, if any , of
<br />any such
<br /> fees and charges of engineers , architects , attorneys , adjustment, a Claim may be made therefor as
<br /> and other professionals and all court or arbitration or provided in paragraph 10 . 05 .
<br /> other dispute resolution costs) arising out of or
<br /> relating to any infringement of patent rights or 6 . 10 Taxes
<br /> copyrights incident to the use in the performance of
<br /> the Work or resulting from the incorporation in the A. CONTRACTOR shall pay all sales , consum-
<br /> Work of any invention , design , process , product, or er, use , and other similar taxes required to
<br /> be
<br /> device not specified in the Contract Documents , paid by CONTRACTOR in accordance with
<br /> the Laws and Regulations of the place of the
<br /> Project which are applicable during the
<br /> performance of the Work .