My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
2012-204A
CBCC
>
Official Documents
>
2010's
>
2012
>
2012-204A
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
1/7/2016 10:24:25 AM
Creation date
10/1/2015 4:48:08 AM
Metadata
Fields
Template:
Official Documents
Official Document Type
Contract
Approved Date
11/13/2012
Control Number
2012-204A
Agenda Item Number
8.E.
Entity Name
Timothy Rose Contracting
Subject
Contract Documents Specifications
Federal Aid Project FM #425710-1-28-01
Area
Old Dixie Highway 8th St. to SR 60
Project Number
1102
Supplemental fields
SmeadsoftID
11622
Jump to thumbnail
< previous set
next set >
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
320
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
SECTION 01310 <br /> CONSTRUCTION SCHEDULES <br /> 1 . 1 GENERAL REQUIREMENTS <br /> A. No partial payments shall be approved by the ENGINEER until there is an <br /> approved construction progress schedule on hand . <br /> Be Designate an authorized representative who shall be responsible for <br /> development and maintenance of the schedule and of all progress and <br /> payment reports . This representative shall have direct project control and <br /> complete authority to act on behalf of the CONTRACTOR in fulfilling the <br /> commitments of the CONTRACTOR's schedules . <br /> 1 . 2 REVISIONS TO THE CONSTRUCTION SCHEDULES <br /> When the ENGINEER requires the CONTRACTOR to submit revised (updated) <br /> progress schedules on a monthly basis the CONTRACTOR shall : <br /> A. Indicate the progress of each activity to the date of submission . <br /> Be Show changes occurring since the previous submission listing : <br /> 1 . Major changes in scope. <br /> 2 . Activities modified since the previous submission . <br /> 3 . Revised projections of progress and completion . <br /> 4 . Other identifiable changes . <br /> C . Provide a narrative report as needed to define : <br /> 1 . Problem areas , anticipated delays , and the impact on the schedule . <br /> 2 . Corrective action recommended and its effect . <br /> 3 . The effect of changes on schedules of other prime contractors . <br /> 1 . 3 SUBMISSION OF THE CONSTRUCTION SCHEDULES <br /> On or before the tenth day after the effective date of the Agreement, submit the <br /> initial schedules to the ENGINEER . The ENGINEER will review the schedules <br /> and return a review copy to the CONTRACTOR within 21 days after _receipt . If <br /> required by the ENGINEER , resubmit revised schedules on or before the <br /> seventh day after receipt of the review copy . If required by the ENGINEER , <br /> submit revised monthly progress schedules with that month 's application for <br /> 01310-1 01310 Construction Schedule <br /> FAI?ublic Works\ENGINEERING DIVISION PROJECTS\1102-Old Dixie Hwy Swk 8th St to SR 60-LAPWdmim\bid documents\Master <br /> Contract Documents\01310 = Construction Schedule.doc <br />