DEC -'11976 <br />SCHEDULE <br />Plans and specifications for the Electric Utilities Adjustment construc- <br />tion contract Are complete and ready for the taking of bids. The following <br />is a realistic schedule starting from the point in time when the City is <br />assured of the availability of funding: <br />DAYS <br />Initiate advertisement for bids 0 . <br />Issue plans to prequalified bidders 5 <br />Receive bids 30 <br />Contract award by City Council 40 <br />Contractor mobilize so <br />Contractor receive all material 110 <br />Complete Item I and 11 of the contract 170 <br />Complete Item IV of the contract 200 <br />Complete Item III and entire contract 230 <br />The above listed days are total times from the advertisement for bid. <br />Saw, C103 <br />RMCM 27 au <br />13 <br />