Laserfiche WebLink
1' <br />FUTURE PROJECT COSTS <br />If <br />In accordance with the approved construction/operational plans for the new sanitary landfill facility, the <br />net useable land (land on which solid waste will be disposed) consists of approximately 100 acres or about 50 <br />percent of the site's total available land area 090 acres). These 100 acres of "net -useable -land" will be developed <br />in four segments or phases. The first segment, consisting of approximately 25 acres, will be developed (i.e., <br />cleared, filled, graded, etc.) under the 1977-78 construction program. It should provide sufficient landfill space to <br />accommodate the disposal of all solid waste generated within Indian River County over approximately the next 5 <br />years. The remaining three segments will be individually developed, as required, in sequence, according to the <br />approved construction/operational plans to provide continuous solid waste disposal service over the projected <br />useful life of the site. The cost to develop each of the remaining three segments, including clearing and grubbing <br />of the land, filling and grading to prescribed grade elevations, and the construction of perimeter roads, ditches <br />and berms, has been estimated in 1976 dollars as follows: <br />Segment No. 2 — $155,000 <br />Segment No. 3 — 172,000 <br />Segment No. 4 — 190,000 <br />Total Estimated Future <br />Capital Improvement Costs $517,000 <br />Based on the projected solid waste generation rates for Indian River County over the next 17 years, the <br />preparation of Segments 2, 3, and 4 should occur in FY 1983-84, FY 1987-88 and FY 1990-91, respectively. It is <br />anticipated that the capital improvement costs to prepare these three segments will be financed by accumulated <br />net system operating revenues generated during the initial years of operation in prior segments and, if necessary, <br />by short-term financing programs (e.g. tax anticipation notes). <br />PROJECTED OPERATING AND MAINTENANCE (O & M) COSTS <br />The annual O & M costs for Indian River County's new central sanitary landfill are estimated on the basis of <br />its projected resource requirements including manpower, equipment, parts and supplies and utilities. These <br />resource requirements were determined in accordance with the proposed operating schedule for the facility and <br />projected rates of incoming solid waste to the facility. Table 4 contains a breakdown of the projected annual O & <br />M costs for the new sanitary landfill during its initial year of operation (FY 1977-78). <br />To realistically project future O & M costs, an average annual inflation rate of 7 percent has been applied to <br />the projections. The projected annual O & M costs for the new landfill are presented in Table. 5. <br />A-$ <br />�....-.. ::. _-:.. -. ,�.: .. «.-_, _ .._:...-.--...::.�.. .:.._._.���-r--.�.:.��a.-�-mac_.-»-..,-_... �-..:-.�*.__.. .gym-.F.�.......�-gt.c.��.ca ..�•,�-..x-+-�x�_..r-c.+r-m ....._ - �.--.. _ -.x-, . r- _ :-:_ .« <br />JAN 181978�� <br />BGGK cT3 PAF.3 '�4' <br />