JUL 161980 <br />Dox 44 PAGE 88 <br />Our review of the entire test well program shows the following: <br />A. The low bidder Alsay-Pippin Corporation is qualified to perform the con- <br />struction. <br />B. The low bid of $116,802.00 (with adjustment for actual quantities used) is <br />below the estimated cost as shown in Item 3 above ($145,000.00). <br />C. The cost for the third production well, if to be constructed under the test <br />well program, based on the low bidder's unit price, is $37,980.00 (same as <br />Bid Item No. 3 - 8 hours pump test). This cost is below the estimated cost <br />as shown in Item 3 above ($50,000.00). <br />D. The overall test well program cost which includes: <br />1. Construction (based on low bid) $116,802.00 <br />2. Third production well 37,980.00 <br />3. Geraghty & Miller fee (approximately) 50,000.00 <br />$204,782.00 <br />The actual total cost will require adjustment for actual quantities of <br />well construction and Geraghty & Miller fee. The allocated cost for this <br />work, as presented in the Joint Venture engineering report, is $258,000.00. <br />Therefore, based upon our review of the entire test well program and associated <br />costs, we are recommending the County to proceed with the program and award the <br />test well construction contract (in conjunction with Geraghty & Miller's recom- <br />mendation) to Alsay-Pippin Corporation. The County should also proceed with the <br />third production well based on the bid price received, if the review of the data <br />obtained during the test well program is favorable. The Joint Venture and <br />Geraghty & Miller will report to the Commission with a recommendation for the third <br />production well at that time. <br />We trust our recommendation meets the Commission's approval. We will be present <br />at the next regular meeting to discuss this program. <br />Very truly yours, <br />ohn A. Robbins <br />For The Joint Venture <br />cc: Mr. Tom Tessier, w/encl. <br />Mr. Ralph Eng <br />Geraghty _& N iller, Inc. <br />CONSULTING GROUND WATER GEOLOGISTS AND HYDROLOGISTS <br />9 July 1980 <br />P225SC2 <br />Indian River County Commissioners <br />c/o Jack Jennings, County Administrator <br />Indian River County Courthouse <br />Vero Beach, FL 32960 <br />Dear Commissioners: <br />Forum Ili <br />Suite 404 <br />1675 Palm Beach Lake, Boulevard <br />West Palm Beach, Flor,da 33401 <br />Telephone: 3051 6833033 <br />On Monday, July 7, 1980, sealed bids were received in the <br />office of the County ladministrator for the construction of <br />a Floridan Aquifer Test Production Well and associated work. <br />Bids were received from four contractors, all qualified and <br />experienced to perform the work required under the contract. <br />The attached Review of Contractors' Bids, lists all bidding <br />contractors and their bid prices. <br />After reviewing the bid documents, bid prices and unit prices <br />of all bidding contractors, Geraghty & Miller believes that <br />it is in the best interest of Indian River County to accept <br />the bid of $116,802.00 from the Alsay-Pippin Corporation. <br />We will be available at the County's convenience to respond <br />to questions and comments regarding this review. <br />Sincerely, <br />GERAGHTY & MILLER, INC. <br />James A. Wheatley for <br />nt P. Am <br />tive Vice President <br />