SC -13.03 Test and Inspections <br />SC -13.03.B. Delete the first sentence of paragraph GC -13.03.8 in its entirety, and insert the <br />following sentences in its place: <br />B. OWNER shall employ and pay for the services of an independent testing laboratory to <br />perform all initial inspections, tests, or approvals required by the Contract Documents <br />except those inspections, tests, or approvals listed immediately below. Subsequent <br />inspections, tests, or approvals required after initial failing inspections, tests, or <br />approvals shall be paid for by the CONTRACTOR by back charge to subsequent <br />applications for payment. The CONTRACTOR shall arrange, obtain, and pay for the <br />following inspections, tests, or approvals: <br />1. inspections, tests, or approvals covered by paragraphs 13.03.0 and 13.03.D <br />below; <br />2. costs incurred in connection with tests or inspections conducted pursuant to <br />paragraph 13.04.B shall be paid as provided in said paragraph 13.04.B; <br />3. tests otherwise specifically provided in the Contract Documents. <br />13.05 OWNER May Stop the Work <br />SC -13.05.A. Delete paragraph GC -13.05.A in its entirety and insert the following paragraph in its <br />place: <br />A. If the Work is defective, or CONTRACTOR fails to supply sufficient skilled <br />workers or suitable materials or equipment, or fails to comply with permit <br />requirements, or fails to comply with the technical specifications, or fails to <br />perform the Work in such a way that the completed Work will conform to the <br />Contract Documents, OWNER may order CONTRACTOR to stop the Work, or any <br />portion thereof, until the cause for such order has been eliminated; however, this <br />right of OWNER to stop the Work shall not give rise to any duty on the part of <br />OWNER to exercise this right for the benefit of CONTRACTOR, any <br />Subcontractor, any Supplier, any other individual or entity, or any surety for, or <br />employee or agent of any of them. <br />14.02 Progress Payments <br />SC -14.02.B.5. Delete paragraph GC -14.02.8.5.d in its entirety and insert the following paragraph <br />in its place: <br />d. ENGINEER has actual knowledge of the occurrence of any of the events <br />enumerated in paragraph 15.02.A; or <br />SC -14.02.B.5. Add the following sentences at the end of paragraph GC -14.02.8.5: <br />e. OWNER has been required to pay ENGINEER additional compensation because <br />of CONTRACTOR delays or rejection of defective Work; or <br />f. OWNER has been required to pay an independent testing laboratory for <br />00800-7 <br />00800 - SupplementaryConditions <br />00800 %F:\Engineering\Capital Projects\0381 Oslo Road Boat Ramp\0381 Contract Documents and Specifications\00800 - Supplementary Conditions.doc <br />