EXHIBIT A <br /> SCOPE OF PROFESSIONAL SERVICES <br /> AMENDMENT NO.4 <br /> INDIAN RIVER COUNTY SOLID WASTE DISPOSAL DISTRICT <br /> OSLO CUSTOMER CONVENIENCE CENTER <br /> The Indian River County Solid Waste Disposal District(IRC SWDD)currently operates a residential <br /> collection/recycling customer convenience center(CCC)at the former Oslo Landfill site.In an effort <br /> to provide an increased level of service to its residents,IRC SWDD is proposing to build a new CCC <br /> at the Oslo site to replace the existing facility.The existing CCC will remain operational until the <br /> new facility is complete.The proposed new facility will be constructed over the old Oslo solid waste <br /> dump site. <br /> The proposed improvements include paved access roads and parking/drive areas,attendant office, <br /> covered household hazardous waste and oil collection/storage area,restroom facilities,and a <br /> retention pond for stormwater treatment and attenuation.Stationary compactors with enclosed <br /> roll-off storage containers are proposed to be used to transport municipal solid waste(MSW)to the <br /> landfill.Open top roll-off containers will be used-to transport cardboard,paper,mixed recyclables, <br /> yard waste,recyclable metals,and tires to the landfill for processing.Household hazardous waste <br /> (HHW)will be collected at the proposed covered HHW and oil collection/storage area. <br /> On December 5,2012,the Contractor was issued a Notice to Proceed construction of the new Oslo <br /> CCC by December 10,2012 and complete the project in accordance with the Contract Time as <br /> follows:Partial Utilization by April 9,2013 (120 days),Substantial Completion by May 9,2013, <br /> (150 days),and Final Completion by June 8,2013 (180 days). <br /> On June 11,2013 IRC approved a Change Order extending the Contract Time to June 22,2013(194 <br /> days)for Partial Utilization,July 22,2013 (224 days)for Substantial Completion,and August 21, <br /> 2013 (254 days)for Final Completion. <br /> Based on an updated schedule received from the Contractor on September 10,2013,Substantial <br /> Completion and Final Completion of the project are anticipated by September 20,2013(284 days) <br /> and October 20,2013 (314 days),respectively. <br /> CDM Smith's current work authorization provides General Engineering Services During <br /> Construction for a 6-month construction period(150 days to substantial completion and 180 days <br /> to final acceptance).This amendment includes General Engineering Services During Construction <br /> for an additional 4.5 months (134 days)to coincide with the construction schedule. <br /> SCOPE OF SERVICES <br /> TASK 5.0-GENERAL ENGINEERING SERVICES <br /> CDM Smith will provide services during construction for the new Oslo CCC.Under this task,CDM <br /> will provide construction services on an as needed basis during construction for the estimated 6- <br /> A-1 jJln%JAmendment4.da <br /> 174 <br />