Laserfiche WebLink
14.02 Progress Payments <br />SC -14.02.B.5. Delete paragraph GC-14.02.B.5.d in its entirety and insert the following paragraph <br />in its place: <br />d. ENGINEER has actual knowledge of the occurrence of any of the events <br />enumerated in paragraph 15.02.A; or <br />SC -14.02.13.5. Add the following sentences at the end of paragraph GC -14.02.8.5: <br />e. OWNER has been required to pay ENGINEER additional compensation because <br />of CONTRACTOR delays or rejection of defective Work; or <br />f. OWNER has been required to pay an independent testing laboratory for <br />subsequent inspections, tests, or approvals taken after initial failing <br />inspections, tests, or approvals. <br />SC -14.02.C.1. Delete paragraph GC -14.02.C.1 in its entirety and insert the following <br />paragraph in its place: <br />C. Payment Becomes Due <br />1. Payment shall be made by OWNER to CONTRACTOR according to the Local <br />Government Prompt Payment Act. F.S. 218.70 et. seq. <br />SC -14.04A. After the third sentence in paragraph GC -14.04A of the General Conditions, <br />delete the remainder of paragraph 14.04A in its entirety and replace with the following: <br />"If Engineer considers the Work substantially complete, Engineer will prepare <br />and deliver to Owner a tentative certificate of Substantial Completion that shall fix <br />the date of Substantial Completion. In accordance with the provisions of Florida <br />Statutes section 208.735(7)(x)(2005), upon receipt of the tentative certificate of <br />Substantial Completion from Engineer, the Owner, the Engineer, and the <br />Contractor shall conduct a walk-through inspection of the Project to document a <br />list of any items required to render the Work on the Project complete, <br />satisfactory, and acceptable under this Agreement (herein the "Statutory List"). <br />The Statutory List shall be reduced to writing and circulated among the Owner, <br />the Engineer, and the Contractor by the Owner or the Engineer within 30 <br />calendar days after substantial completion. The Owner and Contractor <br />acknowledge and agree that: 1) the failure to include any corrective work, or <br />pending items that are not yet completed, on the Statutory List does not alter the <br />responsibility of the Contractor to complete all of the Work under this Agreement; <br />2) upon completion of all items on the Statutory List, the Contractor may submit a <br />pay request for all remaining retainage except as otherwise set forth in this <br />Agreement; and 3) any and all items that require correction under this Agreement <br />and that are identified after the preparation of the Statutory List remain the <br />obligation of the Contractor to complete to the Owner's satisfaction under this <br />Agreement. After receipt of the Statutory List by the Contractor, the Contractor <br />acknowledges and agrees that it will diligently proceed to complete all items on <br />the Statutory List and schedule a final walk-through in anticipation of final <br />completion on the Project." <br />SC -14.0413 Add the following new paragraph immediately after paragraph GC 14.048: <br />00800-s <br />00800 - Supplementary Conditions 05-13 rev.doc <br />00800 9F:\Public Works\ENGINEERING DIVISION PROJECTS\1137-Old Dixie Hwy Resurfacing IRF North Relief Canal to 71st St\Admim\bid documents\Contract <br />Documents\00800 - Supplementary Conditions 05-13 rev.doc <br />