C. If ENGINEER does not render a formal 2. Cost of all materials and equipment
<br /> decision in writing within the time stated in paragraph furnished and incorporated in the Work, includ-
<br /> 10.05.13, a decision denying the Claim in its entirety ing costs of transportation and storage thereof,
<br /> shall be deemed to have been issued 31 days after and Suppliers' field services required in
<br /> receipt of the last submittal of the claimant or the last connection therewith. All cash discounts shall
<br /> submittal of the opposing party, if any. accrue to CONTRACTOR unless OWNER
<br /> deposits funds with CONTRACTOR with which
<br /> D. No Claim for an adjustment in Contract Price to make payments, in which case the cash
<br /> or Contract Times (or Milestones) will be valid if not discounts shall accrue to OWNER. All trade
<br /> submitted in accordance with this paragraph 10.05. discounts, rebates and refunds and returns
<br /> from sale of surplus materials and equipment
<br /> shall accrue to OWNER, and CONTRACTOR
<br /> ARTICLE 11 - COST OF THE WORK; CASH shall make provisions so that they may be
<br /> ALLOWANCES; UNIT PRICE WORK obtained.
<br /> 3. Payments made by CONTRACTOR
<br /> 11.01 Cost of the Work to Subcontractors for Work performed by
<br /> Subcontractors. If required by OWNER, LON-
<br /> A. Costs Included: The term Cost of the Work TRACTOR shall obtain competitive bids from
<br /> means the sum of all costs necessarily incurred and subcontractors acceptable to OWNER and
<br /> paid by CONTRACTOR in the proper performance of CONTRACTOR and shall deliver such bids to
<br /> the Work. When the value of any Work covered by a OWNER, who will then determine, with the
<br /> Change Order or when a Claim for an adjustment in advice of ENGINEER, which bids, if any, will be
<br /> Contract Price is determined on the basis of Cost of acceptable. If any subcontract provides that the
<br /> the Work, the costs to be reimbursed to Subcontractor is to be paid on the basis of Cost
<br /> CONTRACTOR will be only those additional or of the Work plus a fee, the Subcontractor's
<br /> incremental costs required because of the change in Cost of the Work and fee shall be determined
<br /> the Work or because of the event giving rise to the in the same manner as CONTRACTOR's Cost
<br /> Claim. Except as otherwise may be agreed to in of the Work and fee as provided in this para-
<br /> writing by OWNER, such costs shall be in amounts no graph 11.01.
<br /> higher than those prevailing in the locality of the
<br /> Project, shall include only the following items, and 4. Costs of special consultants
<br /> shall not include any of the costs itemized in para- (including but not limited to engineers,
<br /> graph 11.01.13. architects, testing laboratories, surveyors,
<br /> attorneys, and accountants) employed for
<br /> 7 Payroll roc+c for employees in +ho services specifically related to the Work.
<br /> manGe of the 1.4.lerl. under 613hedules of job 5. Supplemental costs including the
<br /> agreed upc)n by OWNER and following:
<br /> superintendents, feremen, a. The proportion of necessary trans-
<br /> and- A_t..h.eF PeFSORnel employed full time at the travel, and subsistence expenses of
<br /> Site. PaYFE)II GGStS for employees not employed CONTRACTOR's employees incurred in dis-
<br /> charge of duties connected with the Work.
<br /> thebasisP-)f their tome on the %^�.A-1:k.
<br /> Payroll GA-StS 16h@11 inrdlude, but not be limited , b. Cost, including transportation and
<br /> salaries and wages plus the ^oc+ of frin^o maintenance, of all materials, supplies, equip-
<br /> ment, machinery, appliances, office, and
<br /> temporary facilities at the Site, and hand tools
<br /> payroll taxes, werkeFS' health not owned by the workers, which are consumed
<br /> of
<br /> and ro+iromon+ hon +c ,�
<br /> h^nena cir•4 loayo in the performance of the Work, and cost, less
<br /> market value, of such items used but not con-
<br /> Tho expenses of norferminn VVE)Fk eutside of sumed which remain the property of CON-
<br /> regular wGrking heuFs, en Saturday, Sunday, or
<br /> legal holidays, shall be the above to
<br /> the extent autherized by OWNER.
<br /> 00700-General Conditions REV 5-10-13.doc
<br /> 00700-32
<br /> F1Public Works\ENGINEERING DIVISION PROJECTS\084513-Old Dixie Hwy Sidewalk(38th Ln-45th St)\Admim\bid documents\Master Contract Documents\00700-General Conditions
<br /> REV 5-10-13.doc