Laserfiche WebLink
22. SPECIAL PROVISIONS <br /> The Contractor shall comply with the following special provisions as part of the contract for the Old <br /> Dixie Highway Sidewalk Project.- <br /> (1) <br /> roject:(1) (A) BASE BID - TIMEFRAME <br /> The total time for the project construction will commence with a Written Notice to <br /> Proceed from the County that is anticipated to be issued to the Contractor on <br /> November 10, 2014 with the project being substantially completed by the Contractor <br /> on the 60th day and totally 100% completed by the Contractor on the 75th day. <br /> (B) CPM SCHEDULE AND NARRITIVE <br /> The Contractor shall submit to the County as part of his bid submission, a detailed <br /> construction schedule in CPM format outlining the proposed progress of the work to <br /> be performed by the Contractor and his subcontractors for the BASE BID — <br /> TIMEFRAME. <br /> The Contractors CPM schedule for the BASE BID—TIMEFRAME shall include but <br /> not be limited to the demolition phasing dates of the work, manufacturing dates of all <br /> components, all phasing dates of the total work required for each component to be <br /> manufactured and installed, the start and completion dates for each phase of the <br /> individual components to be installed, street closure dates and durations including <br /> the start and completion dates of each phase. <br /> In addition to the CPM schedule for the BASE BID—TIMEFRAME, the Contractor <br /> shall submit, in narrative format, a detailed description of the means and methods <br /> for the Contractor's work including but not limited to the mobilization and <br /> demobilization of all equipment and materials, the demolition sequencing of the <br /> work, the individual phasing sequencing of each component manufacturing and <br /> installation, the Contractor's proposed manpower and equipment allocations and <br /> commitments for each phase of the work, the Contractor's proposed work hours for <br /> each day to be worked, the phasing of road closures with their closure dates and <br /> durations, work sequence and days of the week the Contractor and his <br /> subcontractors will require from the County to complete the work within the time <br /> frames of the BASE BID—TIMEFRAME. <br /> The CPM schedules for the BASE BID— TIMEFRAME and narrative approach for <br /> the project will be used by the County in determining the best value in awarding the <br /> construction contract. <br /> The contractor will not be allowed to change his submitted CPM schedule for the <br /> BASE BID—TIMEFRAME prior to and or after the Award of Contract and the Notice <br /> to Proceed is issued by the County without prior written approval of the County's <br /> Project Manager. <br /> (2) The Contractor shall provide daily clean up of the project work area. Cleanup shall include <br /> but not be limited to removal of trash, construction debris, excavated materials and materials <br /> generated as a result of the demolition of the existing sidewalks, curbs and gutters, road way <br /> components. <br /> 54 <br />