Laserfiche WebLink
ARCHITECTURAL/ENGINEERING PROPOSAL <br /> INDIAN RIVER COUNTY SHERIFF'S OFFICE <br /> FENCE/WALL/PAVING/WAREHOUSE EXPANSION <br /> May 02,2013 <br /> PROJECT NO.2011,01,11 <br /> Page 6 <br /> Prepare site stormwater grading and drainage improvement modifications to support this project. Plans will <br /> depict the finished floor elevation for the warehouse expansion, as well as grades for all paving, pedestrian <br /> walks, wall foundations, and drainage features. As a result of the newly planned warehouse, existing <br /> stormwater management systems will need to be modified to support this project. <br /> It is understood that no water and/or wastewater improvements are needed to support this project. Also, it is <br /> understood that fire protection for the 1,700 sf warehouse expansion can be accomplished by connection to the <br /> existing building fire system. <br /> Task C — Site Plan Approval & Permitting Applications: Prepare an application for Major Site Plan <br /> Modification Approval to allow for construction of the proposed improvements. The application will be <br /> submitted to Indian River County supported by the Site Construction Plans,as well as Phasing Plans. As the <br /> project does not propose any additional residential units and impervious surface additions will be(much)less <br /> than 150,000 square feet,this application may be approved by the County Planning Department staff. <br /> Following submittal of the Major Site Plan application,the Engineer shall attend the County Technical Review <br /> Committee(TRC)meeting to obtain any comments and concerns regarding the application. <br /> In addition to the Major Site Plan application, the Engineer shall make applications to obtain approvals / <br /> permits from the following regulatory agencies to support this project: <br /> Indian River County Land Clearing Permit <br /> Indian River County Tree Removal Permit(if required) <br /> Indian River County Type A Stormwater Permit Modification <br /> St.Johns River WMD ERP Modification <br /> Application fees associated with application submittals will be provided by the Client, and have not been <br /> included in this proposal. <br /> Task D—Permitting: It is anticipated that following the review of applications,permitting agencies will issue <br /> Requests for Additional Information(RAI's)to support issuance of construction permits. Under this task the <br /> Engineer shall prepare the responses to RAI's to address the agencies concerns in order that a Site Plan Release <br /> may be issued by the Indian River County Community Development Department. <br /> CONSTRUCTION SERVICES: <br /> Task E-Shop Drawing Review/Pre-Construction Meeting: Review all shop drawings and submittals for <br /> site work construction pertaining to stormwater and paving systems. <br /> Coordinate with the Contractor and his sub-contractors and Indian River County Personnel to set up the <br /> required pre-construction meeting. The"pre-con"provides an opportunity for the County to offer instructions <br /> regarding areas of special concern and to describe the construction inspection and project completion <br /> procedures. <br /> Task F - On-Site Construction Observation: During construction of the site improvements by the <br /> Contractor, the Engineer will perform sufficient construction observation at our discretion on an as-needed <br /> basis such that we can certify the construction of the phased improvements. Formal inspections require forty- <br /> eight(48)hours notice prior to procedure. <br /> D 0 N A D 1 0 <br /> & Associates, Architects, P.A. <br /> 63 <br />