ARTICLE 15 - SUSPENSION OF WORK AND <br />TERMINATION <br />15.01 OWNER May Suspend Work <br />A. At any time and without cause, OWNER may <br />suspend the Work or any portion thereof for a period <br />of not more than 90 consecutive days by notice in <br />writing to CONTRACTOR and ENGINEER which will <br />fix the date on which Work will be resumed. CON- <br />TRACTOR shall resume the Work on the date so <br />fixed. <br />cucpension if CONTRACTOR makes a Claim therefor <br />ef. <br />15.02 OWNER May Terminate for Cause <br />A. The occurrence of any one or more of the <br />following events will justify termination for cause: <br />1. CONTRACTOR's persistent failure <br />to perform the Work in accordance with the <br />Contract Documents (including, but not limited <br />to, failure to supply sufficient skilled workers or <br />suitable materials or equipment or failure to <br />adhere to the progress schedule established <br />under paragraph 2.07 as adjusted from time to <br />time pursuant to paragraph 6.04); <br />2. CONTRACTOR's disregard of Laws <br />or Regulations of any public body having <br />jurisdiction; <br />3. CONTRACTOR's disregard of the <br />authority of ENGINEER; or <br />4. CONTRACTOR's violation in any <br />substantial way of any provisions of the <br />Contract Documents. <br />B. If one or more of the events identified in <br />paragraph 15.02.A occur, OWNER may, after giving <br />CONTRACTOR (and the surety, if any) seven days <br />written notice, terminate the services of <br />CONTRACTOR, exclude CONTRACTOR from the <br />Site, and take possession of the Work and of all <br />CONTRACTOR's tools, appliances, construction <br />equipment, and machinery at the Site, and use the <br />same to the full extent they could be used by <br />CONTRACTOR (without liability to CONTRACTOR for <br />trespass or conversion), incorporate in the Work all <br />materials and equipment stored at the Site or for <br />which OWNER has paid CONTRACTOR but which <br />are stored elsewhere, and finish the Work as OWNER <br />may deem expedient. In such case, CO <br />shall not be entitled to receive any furt <br />until the Work is finished. If the unpaid b. <br />Contract Price exceeds all claims, costs, <br />damages (including but not limited to <br />charges of engineers, architects, attorney <br />professionals and all court or arbitrati <br />dispute resolution costs) sustained by 0 <br />out of or relating to completing the Work, <br />will be paid to CONTRACTOR. If such cl <br />losses, and damages exceed such unp <br />CONTRACTOR shall pay the difference <br />Such claims, costs, losses, and damages <br />OWNER will be reviewed by ENGINEE <br />reasonableness and, when so ap <br />ENGINEER, incorporated in a Change 0 <br />exercising any rights or remedies <br />paragraph OWNER shall not be required <br />lowest price for the Work performed. <br />TRACTOR <br />er payment <br />lance of the <br />losses, and <br />II fees and <br />, and other <br />n or other <br />NER arising <br />uch excess <br />ims, costs, <br />id balance, <br />o OWNER. <br />incurred by <br />as to their <br />•roved by <br />der. When <br />under this <br />o obtain the <br />0 <br />C. Where CONTRACTOR's service have been <br />so terminated by OWNER, the termina ion will not <br />affect any rights or remedies of OWNER against <br />CONTRACTOR then existing or which m thereafter <br />accrue. Any retention or payment of oneys due <br />CONTRACTOR by OWNER will not rel ase CON- <br />TRACTOR from liability. <br />15.03 OWNER May Terminate For Con enience <br />A. Upon seven days written notic- to CON- <br />TRACTOR and ENGINEER, OWNER ay, without <br />cause and without prejudice to any of er right or <br />remedy of OWNER, elect to terminate t e Contract. <br />In such case, CONTRACTOR shall be p=id (without <br />duplication of any items): <br />1. for completed and acce•table Work <br />executed in accordance with th Contract <br />Documents prior to the effecti e date of <br />termination, including fair and reaso able sums <br />for overhead and profit on such Wo ; <br />2. for expenses sustained .rior to the <br />effective date of termination in performing <br />services and fumishing labor, materials, or <br />equipment as required by the Contract <br />Documents in connection with u completed <br />Work, plus fair and reasonable sums for <br />overhead and profit on such expens-s; <br />3. for all claims, costs, I <br />damages (including but not limited <br />and charges of engineers, architect' <br />and other professionals and al <br />arbitration or other dispute resolutio <br />curred in settlement of terminate <br />with Subcontractors, Suppliers, and <br />11 <br />sses, and <br />to all fees <br />, attorneys, <br />court or <br />costs) in - <br />contracts <br />thers; and <br />11 <br />00700 - General Condition REV 5-10-13.doc <br />00700 - 42 <br />F:\Public Works\ENGINEERING DIVISION PROJECTS\1314-107th Ave Milling90th St to 94th St\Admin\bid documents\Master Contract Documents\00700 - General Co <br />13.doc <br />itions REV 5-10- <br />