Laserfiche WebLink
B. Nothing in this paragraph 12.06 bars a 3 as-$ Ienrriss ^nom !;y-prGvWed-ire <br /> change in Contract Price pursuant to this Article 12 to the GeRtraet-DeeWmeRts- <br /> compensate CONTRACTOR due to delay, <br /> interference, or disruption directly attributable to C. If Laws or Regulations of any public body <br /> actions or inactions of OWNER or anyone for whom having jurisdiction require any Work (or part thereof) <br /> OWNER is responsible. specifically to be inspected, tested, or approved by an <br /> employee or other representative of such public body, <br /> CONTRACTOR shall assume full responsibility for <br /> ARTICLE 13-TESTS AND INSPECTIONS; arranging and obtaining such inspections, tests, or <br /> CORRECTION, REMOVAL OR ACCEPTANCE OF approvals, pay all costs in connection therewith, and <br /> DEFECTIVE WORK furnish ENGINEER the required certificates of inspec- <br /> tion or approval. <br /> 13.01 Notice of Defects D. CONTRACTOR shall be responsible for <br /> arranging and obtaining and shall pay all costs in <br /> A. Prompt notice of all defective Work of which connection with any inspections, tests, or approvals <br /> OWNER or ENGINEER has actual knowledge will be required for OWNER's and ENGINEER's acceptance <br /> given to CONTRACTOR. All defective Work may be of materials or equipment to be incorporated in the <br /> rejected, corrected, or accepted as provided in this Work; or acceptance of materials, mix designs, or <br /> Article 13. equipment submitted for approval prior to <br /> CONTRACTOR's purchase thereof for incorporation <br /> 13 02 Access to Work in the Work. Such inspections, tests, or approvals <br /> shall be performed by organizations acceptable to <br /> A. OWNER, ENGINEER, ENGINEER's Con- OWNER and ENGINEER. <br /> sultants, other representatives and personnel of <br /> OWNER, independent testing laboratories, and E. If any Work (or the work of others) that is to <br /> governmental agencies with jurisdictional interests will be inspected, tested, or approved is covered by CON- <br /> have access to the Site and the Work at reasonable TRACTOR without written concurrence of ENGI- <br /> times for their observation, inspecting, and testing. NEER, it must, if requested by ENGINEER, be uncov- <br /> CONTRACTOR shall provide them proper and safe ered for observation. <br /> conditions for such access and advise them of <br /> CONTRACTOR's Site safety procedures and F. Uncovering Work as provided in paragraph <br /> programs so that they may comply therewith as 13.03.E shall be at CONTRACTOR's expense unless <br /> applicable. CONTRACTOR has given ENGINEER timely notice <br /> of CONTRACTOR's intention to cover the same and <br /> 13.03 Tests and Inspections ENGINEER has not acted with reasonable prompt- <br /> ness in response to such notice. <br /> A. CONTRACTOR shall give ENGINEER timely <br /> notice of readiness of the Work for all required 13.04 Uncovering Work <br /> inspections, tests, or approvals and shall cooperate <br /> with inspection and testing personnel to facilitate A. If any Work is covered contrary to the written <br /> required inspections or tests. request of ENGINEER, it must, if requested by ENGI- <br /> NEER, be uncovered for ENGINEER's observation <br /> B. OWNER shall empley and pay fGF-tand replaced at CONTRACTOR's expense. <br /> senriges of an ii;denendent testing Iab Fatory to <br /> B. If ENGINEER considers it necessary or <br /> advisable that covered Work be observed by ENGI- <br /> NEER or inspected or tested by others, CONTRAC- <br /> 4 for inspe^tions tests or appFevals. TOR, at ENGINEER's request, shall uncover, expose, <br /> Govered by paFagraphr, 13.93.G and . or otherwise make available for observation, inspec- <br /> tion, or testing as ENGINEER may require, that <br /> portion of the Work in question, furnishing all neces- <br /> th.,t gg^t^ incurred in ban e^tien with sary labor, material, and equipment. If it is found that <br /> such Work is defective, CONTRACTOR shall pay all <br /> paragraph 13.04.13 shall be paid as previded iR Claims, costs, losses, and damages (including but not <br /> said paFagraph 43.04.B; and limited to all fees and charges of engineers, architects, <br /> attorneys, and other professionals and all court or <br /> 00700-General Conditions REV 5-10-13 <br /> 00700-36 <br /> P\Public Works\ENGINEERING DIVISION PROdECTS\1123 43rd Ave Sidewalk Improvements 26th St.to Airport Dr WestlAdmim\bid documentsWiaster Contract Documents\00700- <br /> General Conditions REV 5-10-13.doe <br />